ABSTRACT
The report concern with the continuation of the
previous pre brief report which focuses on construction of residential house
for University staff especially lecturers at survey quarters
The aim of the project is reduce the problem of
accommodation for staffs of University of Dar es salaam also to achieve
government objective to provide accommodations to its servants.
This report contain four chapters, chapter one is
about introduction of the project, chapter two explain about the site in
details such as site accessibility, site location, site features also it
explain challenges in site, chapter three explain about deficiencies in brief
workshop also general deficiencies in pre brief and brief workshop, chapter
four contain conclusion and recommendations, chapter five and the last one describe
rooms details in room data sheet format
CHAPTER ONE
INTRODUCTION
The project focuses on the designing of a
residential house to be used as Lecturer’s house. This project was selected for
the purpose of meeting the accommodation needs of university stuff particularly
lecturers from the University of Dar-es-salaam.
It’s located along university road which provide
easy access and the neighbors are other staff members {survey quarters}.
The report will cover several things
Ø Site
details
i.
Site location
ii.
Site accessibility
iii.
Site features
iv.
Site restrictions
Ø Room
data sheet
Ø Deficiencies
of brief workshop report
Ø Deficiencies of pre brief and brief workshop
report
Ø Conclusion
Ø Recommendations
CHAPTER TWO
SITE DETAILS
Site location
It’s located along university road for easy access
and the neighbors are other staff members {survey quarters)
Site features
The
site has a flat ground with sand and clay covered with vegetation (trees and
grasses)
Surrounding feature
Are the useful or
advantageous factors or features present around the site, such as electricity,
railroad, roads and water, the following is list of utilities found at site.
o
Electricity
o
Water supply system
o
Sewage system
o
Road infrastructure
Site accessibility
It’s located along
university road which makes it easier to access through main road. The site is
accessible
Challenges
·
The site is accessed at one side only
(front side only)
·
Size of the site with respect to size of
project
CHAPTER THREE
DEFICIENCIES OF OUR PROJECT FROM THE CHECKLIST
Arrangements of
facilities with respect to space example in bedroom1&2 the bed almost cover
half of the room,
Also the arrangement of
rooms are not in particularly combination or form, example the rooms/space
should be allocated as either wet or dry area in which toilets and kitchen
should be located at wet area and bedrooms, sitting room, dining room should be
located as dry area. Also there are private area exposed to public areas like
master bedroom position is not private but rather public area
A lot of free space
which is not economical example the space taken by corridor between toilets and
master bedroom has no use, it is just for the m.bedroom door only, also toilet
and bathroom take a lot of space since 1.000m by 1.500m will be enough for
toilet or it could be combined as the toilet in master bedroom.
THE OVERALL DEFICIENCIES IN PRE-BRIEF AND BRIEF WORKSHOP
In pre-brief the
designer did not design rooms for guests (boys and girls) which become
inconvenience to the end user since he or she will have some guests and they might
need a place to stay for a while
Also designer design for septic and soak away pit
while there is public sewage system, hence the designer did not consider
surrounding features of the area.
Also in brief workshop there is some design problems
like arrangement of the rooms, effective use of space
CHAPTER FOUR
CONCLUSION
In pre brief workshop we established general
problems of design according to purpose and objective of the project also
requirements of the client (university of Dar es Salaam) but in brief It goes
deeper in details about rooms and what they contain inside as respect to their
purpose
So future project should consider every deficiency
in this project so as to get better project and achieve value for money
Including value management procedures since the
start of the project will also contribute much in achieving value for money
RECOMMENDATION
The designer of the structure should ensure the
design comply with client requirements and should check on surrounding features
that may be useful to client .
CHAPTER FIVE
ROOM DATA SHEET
UNIT
|
ROOMS
|
ITEM
|
DESCRIPTION
|
|||
1.
|
LOUNGE
|
Furniture
|
·
Three sofa
·
Coffee table
|
|||
|
|
Electrical
appliances
|
·
Ceiling rose light
·
Air conditioner
·
Light switch
·
Ac switch & regulator
·
socket outlet
·
television
·
|
|||
|
|
Mechanical
appliances
|
·
Wall mounted watch
|
|||
|
|
Sanitary
appliances
|
·
None
|
|||
|
|
Finishes
|
·
Walls: Painted Plastered Wall
·
Floors: Non-Slippery Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
|
|||
|
|
|
|
|||
|
DINING
|
Furniture
|
·
dining table
·
6 dining chairs
·
China cabinet
|
|||
|
|
Electrical
appliances
|
·
Ceiling rose light
·
fan
·
Light switch
·
fan switch & regulator
·
1 socket outlet
|
|||
|
|
Mechanical
appliances
|
·
None
|
|||
|
|
Sanitary
appliances
|
·
hand washing basin
·
soap dispenser
|
|||
|
|
Finishes
|
·
Walls: Painted Plastered Wall
·
Floors: Non-Slippery Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
|
|
|
|
UNIT
|
ROOMS
|
ITEM
|
DESCRIPTION
|
|||
|
MASTER
BEDROOM
|
Furniture
|
·
1 twin bed
·
Wardrobe
·
Bedroom table &chair
|
|||
|
|
Electrical
appliances
|
·
Ceiling rose light
·
1 fan
·
2 Light switch (1gang 2way)
·
fan switch & regulator
·
1 socket outlet
|
|||
|
|
Mechanical
appliances
|
·
None
|
|||
|
|
Sanitary
appliances
|
·
None
|
|||
|
|
Finishes
|
·
Walls: Painted Plastered Wall
·
Floors: Non-Slippery Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
|
|||
|
|
|
|
|||
|
BEDROOM
1
|
furniture
|
·
1 twin bed
·
Wardrobe
|
|||
|
|
Electrical
appliances
|
·
Ceiling rose light
·
1 fan
·
2 Light switch (1gang 2way)
·
fan switch & regulator
·
1 socket outlet
|
|||
|
|
Mechanical
appliances
|
·
None
|
|||
|
|
Sanitary
appliances
|
·
None
|
|||
|
|
finishes
|
·
Walls: Painted
Plastered Wall
·
Floors: Non-Slippery
Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
·
|
|||
|
|
|
|
|||
|
|
|
|
|||
UNIT
|
ROOMS
|
ITEM
|
DESCRIPTION
|
|||
|
KITCHEN
|
Furniture
|
·
Granite table
·
Cabinets
·
racks
|
|||
|
|
Electrical
appliances
|
·
Light bulb
·
Light switch (1gang 1way)
·
Cooker control unit
·
1 twin socket outlet
|
|||
|
|
Mechanical
appliances
|
·
Dish washer
·
Cooker
·
Water heater
|
|||
|
|
Sanitary
appliances
|
·
Hand washing basin
|
|||
|
|
Finishes
|
·
Walls: Painted
Plastered Wall
·
Floors: Non-Slippery
Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
·
Concrete table: granite
floor tiles
|
|||
|
|
|
|
|||
|
TOILETS
&BATHROOM
|
Furniture
|
·
None
|
|||
|
|
Electrical
appliances
|
·
Light bulb
·
Light Switch (2 gang 1 way) for public toilet
·
Light switch (1 gang 1 way) for m-bedroom bathroom
|
|||
|
|
Mechanical
appliances
|
·
None
|
|||
|
|
Sanitary
appliances & fixture
|
·
Wall mounted shower
·
WC western type fixed to floor for public and
m-bedroom toilets
·
Soap dispenser
·
Hand wash basin
·
Towel rails& holders
|
|||
|
|
Finishes
|
·
Walls: Non-Slippery
Porcelain wall Tiles Ex-China
·
Floors: Non-Slippery
Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
|
|||
UNIT
|
ROOMS
|
ITEM
|
DESCRIPTION
|
|||
|
PASSAGE
TO REAR VERANDAH
|
Furniture
|
·
None
|
|||
|
|
Electrical
appliances
|
·
Light bulb
·
Light Switch (1gang 2 way)
|
|||
|
|
Mechanical
appliances
|
·
None
|
|||
|
|
Sanitary
appliances
|
·
None
|
|||
|
|
Finishes
|
·
Walls: Painted
Plastered Wall
·
Floors: Non-Slippery
Porcelain Floor Tiles Ex-China
·
Ceilings: Gypsum
Board Ceiling Ex-Thailand
|