UNIVERSITY OF DAR
ES SALAAM
COLLEGE OF
ENGINEERING AND TECHNOLOGY (CoET)
DEPARTMENT OF
STRUCTURAL AND CONSTRUCTION MANAGEMENT
NAME: MNYANYEMBE ISMAIL A
REG No. 2016-04-08652
COURSE: BSc IN
QUANTITY SURVEYING
YEAR OF STUDY: 2nd
YEAR
FIRM: NEW AGE
CONSTRUCTION
PRACTICAL
TRAININING (PT2)
DURATION PERIOD: 8
WEEKS
TRAINING OFFICER:
Eng GIFT NGOMUO
SUPERVISOUR NAME:
TABLE OF CONTENTS
PREFACE ………………………………………………………………………………………….
DECLARATION…………………………………………………………………………………...
AKNOWLEDGEMENT……………………………………………………………………………
PART1: GENERAL
REPORT………………………………………………………….………….
Introduction of the Firm ….…….……………….………………………………….…………..
PROJECT SUMMARY …………………………………….………..…
PART 2:
LOG BOOKS AND WEEKLY SUMMARY…………………………………...........
WEEK 1: …...…...
WEEK 2; …………………………………………...……
WEEK 3: …………….………………………………...………………..
WEEK 4: …………..………………..………………..………………..……
WEEK 5: …………………….....…………….…..
WEEK 6: ……………………………………...…………………………..............................
WEEK 7; …………………..….……………………………………………………………..
WEEK 8; ………………..……………………………………………………………………
PART 3: SPECIFIC
REPORT…………………………………………………………………….
PART 4: GENERAL
CONCLUTION……………………………………………………………
DECLARATION
This
report was prepared by MNYANYEMBE ISMAIL A a quantity surveying second year
student at University of Dar es salaam, who declare that all the information
covered in these report are from sites activities and information from site
engineers and company managing director. This report is about the construction
of CARMEL SCHOOL at olasiti, Arusha.
Declare
to be faithful to,
........................... ………………………………
ENG.
ROGATH MCHAU
ENG. GIFT NGOMUO
Managing
director
Site engineer
PREFACE
Practical training (PT)
is the part of four years while studying Bsc. Quantity surveying course offered
by the college of engineering and technology (COET) of the University of Dar-es
salaam. It conducted after second semester of the first, second and third year
of studies and is extended over the period of 8 weeks
Practical training has
the following main objectives or purposes
·
To improve and provide knowledge on how
to use some tools and equipments effectively
·
To develop abilities in terms of
communicating, planning, organizing
·
To increase hard working and efficiency
·
To learn more about future career
Practical training help
students to relate all theories learned in class to the real life/ practically.
During this students will be aware with many things concerning their future
profession.
Also it helps students to gain more apart from
those they learned from lecture rooms, college workshop or laboratories. Also
the problems that will face the students will help him/her to overcome to the
future.
The report is detailed
descriptions of craftsman’s level in practical training level in a company
named as NEW AGE CONSTRUCTION COMPANY.
The report explains about the project
conducted for the purpose of school development at CARMEL SCHOOL
ACKNOWLEDGEMENT
First, I would like to
give thanks to God for his blessing and power he always gives to me for superb
energy and willingness I had in my practical training period
Also I would like
extend special thanks to New Age Construction Company for giving me chance to
train in their activities. The staff was very supporting in every way possible
to help me learn and practice and acquire knowledge.
Special thanks to the
department of structural and construction engineering for creating and
facilitating this great opportunity to learn from a practical perspective and
knowledge obtained at class and therefore give me a real perspective of
applications of building construction in practical applications.
Also I would like
extend my appreciation to my family that supported me during all the time at
home and for every means in my training. Their undying support and advice on
office behavior contributed to the success of my training at New Age
Construction Company.
Also I would like to
express my gratitude to several individuals starting with my supervisor for
guiding and challenging me during the training,
Mr. Brian Maganga (managing manager)
Mr. Gift Ngomuo (site engineer)
GENERAL INFORMATION OF
THE COMPANY
NEW AGE CONSTRUCTION COMPANY is a
multidisciplinary Local Construction company, founded and registered in
Tanzania with Engineer’s Registration Board (ERB) in 2004 as Local Engineering
Consulting Firm. NCL is also a member of the Association of Consulting
Engineers (Tanzania) (ACET); the association is affiliated to FIDIC.The firm is wholly owned by MR GODSON J NGOMUO and is also legally registered under the Companies Ordinance (Cap. 212) and currently operating through its office located at Arusha city center, located at OLOSIVA/KIRANYI
VISION
NEW AGE CONSTRUCTIN has the vision of being the Best Engineering Company to all of its Clients. To attain its vision and maintain it, the company has a set of nine core values which are:-
NEW AGE CONSTRUCTIN has the vision of being the Best Engineering Company to all of its Clients. To attain its vision and maintain it, the company has a set of nine core values which are:-
Ø Client's Satisfaction
Ø Flexibility
Ø Openness and Transparency
Ø Team work
Ø Ethics Integrity and Professional conduct
Ø Best quality in construction
Ø Affordability
Ø External region branches expansion
Ø Employment opportunity availability
MISSIONS
Ø
To exceed Client's expectations by
providing quality services within the given time frame work.
Ø
Also high efficiency in construction
and reaching the contemporary world standards.
Ø
The company also aims at conserving
the environment and creating the harmless atmosphere for the beneficiaries of
the projects conducted.
These missions have always been
possible due to the pre mentioned core values the company has. It is these
missions that are taking the company to the fore front of multi-disciplinary
engineering projects and management practices.
CULTURE
AND VALUES
Ø Social
responsibility
Ø Quality
and best practice
Ø Customer
focused
Ø Professionalism
and Ethical conduct
Ø Innovation
and Entrepreneurship
Ø Commitment
Ø Team
work
Ø Environment
friendly
Ø Accountability
Ø Value
for Money
Ø Learning
agency
Ø Gender
Sensitive
Ø Fighting
against Corruption and HIV&AIDS pandemic
PROJECT
SUMMARY
Purpose
of the project:
Project
stake holders:
CLIENT: THE
SISTERS OF APOSTOLIC CARMEL
ARCHITECT: TERRESTIAL
ARCH CONSULTANCY
QUANTITY SURVEYOR: CONSTRUCTION SOLUTIONS LTD
ENGINEER: DOVE ENGINEERING TANZANIA LTD
MAIN ACTIVITIES OF THE
PROJECT
Below
is a description of the main construction works performed during the training
period;
Ø This
activity involves clear site of small bushes, undergrowth and the like grubbing
their roots and store in spoil heap
v Removal of top soil
Ø This
activity involves excavates average 150mm deep to remove top vegetable soil and
stock pile on site for later re- use.
v Earth filling and compaction
Ø This
activity involves filling of good soil around foundation.
Ø Leveling
of soil was followed
Ø Sprinkling
of water around foundation
Ø Compaction
was done to ensure well leveling and to increase the strength of soil
v Preparation of hardcore bed
Ø This
activity includes 200mm bed, leveled and blinded to receive polythene membrane
v Preparation of Concrete works grade
25 of 1:1.5:3
Ø Concrete
was casted to spread on top of hard core bed
Ø Mixing
of sand and course aggregate until mixed within concrete mixer
Ø Put
cement inside a concrete mixer in a required amount
Ø Put
water and admixture inside the concrete mixer in a required amount
Ø Concrete
taken into the required area
v Fixing of reinforcement concrete
work
Ø Cutting
of high tensile bars into the required length
Ø Joining
and shaped of high tensile by using stirrups wires
Ø Overlapping
the R.C into the short R.C column
Ø Fixing
of form work all around the R.C
Ø Casting
and pouring of concrete into the R.C short column and beam
v Erection of walling
Ø Fixing
of damp-proof course to prevent rise of moisture
Ø Preparation
of mortar (1:4) was followed
Ø Solid
concrete block wall bedded and jointed with prepared mortar
Ø Leveling
of block wall
v fixing of metal rank shelves
Ø Cutting
of high tensile bars into the required length
Ø Fixing
of horizontal high tensile bars to the vertical tensile bars by using steel
wires
Ø Leveling
of horizontal high tensile bars
v Construction of form works
Ø Cut
marine board into the size which is similar to the ring beam
Ø Cut
hard woods for supporting marine board into a required length
Ø Fixing
marine board and supporting hard wood
v Construction of roof slab
Ø Cutting
of high tensile bars into the required length
Ø Joining
and shaped of high tensile by using stirrups wires to form ring beam
Ø Fixing
those ring beam for slab
Ø Fixing
marine board into the ring beam
Ø Then
pouring concrete into the prepared ring beam and form work
INFLUENCE OF ENVIROMENTAL CONDITION.
Ø Sun
during a day
Ø Conducive
for all activities.
CONCLUSION.
Ø All
works and activities were all performed and understood effectively.
BUILDING
MATERIAL USED
Different
materials were used in the construction process. The materials include; Cement,
Coarse and fine aggregates, Steel bars, and Woods (Timber & marine boards)
nails, . Due to its effects depending on the type used, water is described as a
building material in this report. The strength of the concrete used in
construction of various elements on the construction is also described
(specified).
AGGREGATES
Aggregates were well cleaned and free
from dust and they were of quality and nature required. The aggregate used were
coarse aggregates of;
Ø 10mm
max. size, graded, for all “fine” concrete
Ø 20mm
max. size, graded, for all reinforced concrete in beams and for walls and slabs
not greater than 400mm thick.
Ø 40mm
max. size ,graded, for all reinforced concrete walls and slabs in excess of
400mm thick and mass concrete members
CEMENT
It was Ordinary Lucky cement. The
Cement was manufactured in Pakistan.
WOODS
The
woods used were of two types; Cyprus woods (timber) and Marine board. The
Cyprus woods were collected from Iringa region and the marine board was
imported from Bombay (India). The woods were used for shuttering and supporting
the safety nets. The woods used for shuttering were supposed to be free from
knots, splits and other shakes. The newly used woods had the above mentioned
qualities; had neither splits nor knots. The recycled or reused woods had
several splits and knots. The shakes led to the formation of knots on the
surfaces of the finished elements (beams, slabs and columns). These have
adverse effects to the distribution or transfer of the load to the ground.
Knots led to the concentration of the forces (load) at only one point leading
to the failure of the structures subsequently the collapse of the building.
Thus knots should be observed and avoided during any construction process.
STEEL
BARS
Steel
used was from turkey
WATER
water used in construction at site was
the water supplied by the Water Supply Company .The use of this water had the
purpose of avoiding salt water which is commonly underground water.
CONCRETE
The
concrete used in construction of different structures of the construction had
different mixing ratio (grades). For slab beams and columns, it was at the
ratio of 1:1:4 (C30) and for stair it was 1:1.5:3 which is C25
CONCRETE
COVER TO REINFORCEMENTS
The
concrete cover to the reinforcements differed depending on the structure and
its load is to transfer to the ground. When shuttering, the concrete cover was
given by the thickness of the spacer blocks.
WEEK
1 SUMMARY 30/07 -04/07/2018:
COLUMNS
CONSTRUCTION
INTRODUCTION:
A column is the vertical member carrying the
beam and floor loadings to the foundation and is a compression member. The
columns are made with reinforced concrete; also columns are used to determine
the exact position of walls, stairs, and corridors and so on. Since concrete is
strong in compression it may be concluded that provided compressive strength of
the concrete is not exceeded no reinforcement would be required. For this
condition to be true the following conditions must exist:
ü loading
must be axial
ü the
large cross section area
These conditions rarely
occur in framed buildings, consequently bending is included and the need for
reinforcement to provide tensile strength is apparent.
On the site we made 24
columns of rectangular form which have the dimension of 460mm in length, 230mm
in width and 2700mm in height.
v MATERIALS USED:
Ø Cement
Ø Sand
Ø Aggregates
Ø Water
Ø Marine
board
Ø Timber
Ø Steel
bars
Ø Nails
Ø Props
(mirunda trees)
Ø Binding
wires
Ø Oil
v SKILLS AND MAN POWER
On the site there was:
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
Ø Unskilled
labour
.
v PROCEDURES
Ø Setting
out columns was firstly done since the construction of slab by means of dump
level, where by starter bars for columns were erected on the required position.
Then the construction of slab basement followed.
Ø We
then start by fixing the steel bars for columns to the height of second floor
level. We used steel bars of dimension Y16 and for stirrup was Y8. The cutting,
bending and fixing of steel bars were done as per bending schedule.
Ø Fixing
of spacer blocks was the next step; this was done purposely to give a maximum
cover for the concrete.
Ø Since
we received the formworks i.e. timber formworks, which has already being
prepared on the required positions. Timber and nails were used on tighten the
timber formwork. Tighten process was done purposely to prevent grout leakage.
Ø Plumb
bob and measuring tape was then used to ensure that the column formwork stand
vertically without lean on other sides.
Ø Finally
casting of concrete on the column formwork was done, concrete of grade 25 in
ratio of 1:11/2:3 were used. Casting was done in one operation with
the use of mechanical vibrator (pocker) to ensure maximum compaction.
v INFLUENCE OF ENVIRONMENTAL
CONDITIONS
During construction of
columns, the weather conditions were condensate, which allow the labour to work
at the maximum required time..
v SAFETY PRECAUTION
QUALITY: care was
observed during construction and erection so that the required size, position
and finish of concrete are obtained.
v SAFETY:
They were constructed
strong enough to take pressure or weight of the fresh concrete and any other
load without distortion, leakage failure or danger to humans.
In addition helmets,
gloves were strictly advised to be worn throughout the time of column
construction. This was done purposely to protect the labor.
v CONCLUSION:
Column reinforcements should be
anchored horizontally to the beams with enough anchorage length.
The
work was done well per specification and completed as required as an
engineering work it was constructed with, Quality, safety, economic and within
the time.
Figure 1: column construction
WEEK
2 SUMMARY 10/07 -15/07/2017:
CONCRETE PREPARATION
v INTRODUCTION:
Concrete
is a composite construction material composed primarily of aggregate, cement
and water. There are many formulations that have varied properties. The
aggregate is generally coarse gravel or crushed rocks such as limestone, or
granite, along with a fine aggregate such as sand. The cement, commonly
Portland cement, and other cementations materials such as fly ash and slag
cement, serve as a binder for the aggregate. Water is then mixed with this dry
composite which enables it to be shaped (typically poured) and then solidified
and hardened into rock-hard strength.
v SKILLS AND MAN POWER
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
Ø Unskilled
labour
v MATERIAL USED,.
Ø aggregates
Ø sand
Ø Twiga
Cement
v TOOLS AND MACHINERY USED.
Ø Tools:
spade, basin, pocker.
Ø Machinery:
roller pulley concrete mixer. Concrete pump.
v PROCEDURES.
Ø The
material were prepared and the
aggregates were washed as required
Ø Then
the concrete mix machine was switched on and their speed was moderate then the
fine aggregate, course aggregate and cement were batched by volume (nominal
mix) then optimum water was applied to the drum of concrete mixer and the mixer
was left (around 3-4 minutes) to obtain the required mixer
NOTE:
The
concrete ratio depends on the usage for example:
ü 1:3:6
(grade 15) mass concrete for over site concrete.
ü 1:2:4
(grade 20) reinforced concrete
ü 1:11/2:3
(grade 25) reinforced concrete. These ratio was used for our site for column
and suspend slabs (reinforced slabs
v INFLUENCE OF ENVIRONMENTAL
CONDITIONS.
Weather
condition was dry, dry condition was very favorable and the work went smoothly.
The
task was performed at night hence the humidity favored the concreting work and
it didn`t affect the work.
v SAFETY PRECAUTIONS.
Safety
tools used were gumboots, gloves, overcoats and helmets
Safety
precaution taken was
Ø wearing
safety boots, gumboots
Ø wearing
gloves
Ø wearing
over coats and helmets
v CONCLUSION AND RECOMMENDATIONS.
I
recommend that concreting should be done during the night time as to avoid
excessive loss of water from the concrete structure before it is hardened.
Figure 2: concrete preparation
WEEK
3 SUMMARY 17/07 -22/07/2017:
FOUNDATION
WALL CONSTRUCTION
v INTRODUCTION
Foundation
wall carries all imposed loads and transmits the o the ground without
settlement. This foundation wall was constructed by using blocks joined
together by mortar of mixing ration 1:4 (cement to sand).
v OBJECTIVES:
Ø Carry
and transmit all loads ( live and dead) to the ground without failure
Ø Provide
stability and strength of the proposed structure.
v MATERIAL USED
Ø Hard
core Stone
Ø Portland
cement
Ø Sand
Ø Water
v TOOLS USED
Ø Wooden
float
Ø Measuring
tape
Ø Trowels
Ø Spade
and buckets
Ø String
Ø Lump
hammer
v SKILLS AND MANPOWER:
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
Ø Unskilled
labour
v PROCEDURE
Ø Batching
and mixing of required material to form motar to a specified ratio that was 1:4
Ø Marking
out the size (width) of the foundation wall by string and measuring tape.
Ø Wetting
the surface ( mass concrete based on earth) read to receive motar.
Ø Pouring
and spreading of motar on the surface where blocks are expected to be laid on,
spreading at width similar to the width of the foundation wall to be
constructed.
Ø Laying
of blocks on spreader mortal in such a way that they obtain a good bond and
make a joint of about 10mm thick.
Ø Applying
cement mortar to the joints and make sure all joints are fully of motar leaving
no voids between adjacent blocks.
Ø Pouring
and spreading of mortar over the previous constructed block wall for the second
cause of stones.
Ø Cleaning
of tools used keeping the site safely and storing the equipments and tools.
v INFLUENCE OF ENVIRONMENTAL
CONDITIONS.
Ø Weather:
dry and sunny.
Ø The
dry condition was very favorable and the work went smoothly without affecting
the block working process.
Ø The
sunny condition was also good and the walling work was not affected by the condition.
v SAFETY PRECAUTIONS.
Safety
tools used were gumboots, gloves, overcoats and helmets
Safety
precaution taken was
Ø wearing
safety boots, gumboots
Ø wearing
gloves to enable easy carrying of blocks.
Ø wearing
over coats and helmets
v CONCLUSION AND RECOMMENDATIONS.
Since
the blocks used were not of exactly same size they resulted in the bending of
walls and since they were using only floor plan without the section plan, there
were some walls that had to be brocken since they go higher than expected.
Example in the windows, 4 courses were built while they were supposed to be
three. This resulted to the breaking of walls to get three courses.
Therefore
during the blockworking it is recommended to use the blocks with exactly same
size and also to make a good use of section plan.
Figure 3: Foundation Walling
WEEK
4 SUMMARY 24/07 -29/07/2017:
EARTHFILLING AND COMPACTION
I (a) Earth
filling
Ø The
purpose of earth filling is to place back soil into the trenches and opening
surface, this material contain sand, rocks and stones, as well as earth.
Ø After
earth filling process done, leveling of soil was followed
Ø Sprinkling
of water was followed
(b) Compaction process
Ø Is the process by which the porosity of a given form of
sediment is decreased as a result of its mineral grains being squeezed together
by the weight of overlying sediment or by mechanical means.
Ø Compaction
was done to ensure well leveling and to increase the strength of soil
Importance
Of Earth Filling And Compaction Of Soil
Ø Used to create a strong and stable base
Ø Increase
the strength of soil
Ø Increase
the soil density or unity weight
v TOOLS AND MATERIAL USED;
Ø Wheelbarrows
Ø Bucket
Ø Holes
Ø PVC
pipes
Ø Buckets
Ø Soil
compactor machine
v SKILLS AND MANPOWER
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
v SAFETY AND PRECAUTIONS;
Ø Wearing
helmet during all working time
Ø Wearing
gloves
Ø Wearing
boots.
Ø Wearing overall or over coat
v INFLUENCE OF ENVIROMENTAL CONDITION.
Ø Sun
during a day.
Ø Conducive
for all activities.
v CONCLUSION.
Ø All
works and activities were all performed and understood effectively.
Figure 4: Backfilling and Soil Compaction
WEEK
5 SUMMARY 24/07 -29/07/2017:
SEPTIC TANK CONSTRUCTIONS
WORKING
HOURS: 0800 – 1700 hrs
INTRODUCTION
A tank typically
underground in which sewage is collected and allowed to decompose through
bacterial activity before draining by means of soak away or is a chamber made
of concrete fiberglass, PVC or plastic through which domestic wastewater flows
for primary treatment
After excavations of the pit next thing was to
cover the soil with hardcore and damp proof membrane. Then preparations and
concrete casting for the floor finishes. The floor was constructed with slight
slope surface for separation purpose. The next day was to construct walls to
the ground level.
And next was plastering
of septic tank walls, walls were covered with plaster rich in cement in order
to make it suitable in wet condition.
v PROCEDURE:
Ø Excavation
of septic tank and removal of excavated material
Ø Hardcore
fill and spread of gravels to make a firm level
Ø Block
walling to ground level
Ø Plastering
of walls’ sides
v SKILLS AND MANPOWER:
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
Ø Unskilled
labour
v TOOLS AND MACHINES USED:
Ø Scissor
for cutting damp proof course
Ø Tape
measure for measuring different dimensions
Ø Trowel
for mortar works
Ø Plumb
bob to insuring blocks are in same levels
Ø Wheel
barrow for carrying sand
Ø Coats
and hats and boots for safety measures
v INFLUENCE OF ENVIRONMENAL CONDITION
Ø Sun
during a day, this reduce speed of the work
Ø Conductive
for all activities
v SAFETY PRECAUTIONS.
Safety
tools used were gumboots, gloves, overcoats and helmets
Safety
precaution taken was
Ø wearing
safety boots, gumboots
Ø wearing
gloves to enable easy carrying of blocks.
Ø wearing
over coats and helmets
v CONCLUSION.
Ø All
works and activities were all performed and understood effectively.
Figure 5: Septic Tank Construction
WEEK
6 SUMMARY 07/08 - 12/08/2017:
HARDCORE
AND OVERSITE CONCRETE
v INTRODUCTION
Concrete
is the hardened building material created by combining a chemically inert
aggregate (fine and coarse aggregate),a binder (cement) and water in controlled
proportions and of suitable quality.
Ø Cement:
powder produced from clay and chalk or limestone. In general most concrete is
made up with ordinary or rapid hardening cement and it is act as a binder.
Ø Aggregate:
shape, surface texture and grading (distribution of particle size) are factor
which influence the workability and strength of a concrete mix. Fine aggregate
are generally regarded as those materials which pass through 4mm sieve whereas
course aggregate are retained on a 4mm sieve
Ø Water
must be clean and free from impurities which are likely to affect the quality
or strength of the resultant concrete.
Ø Basic
requirement of concrete are:
I.
Appropriate workability
I.
Optimum compactability
II.
Sufficient cohesiveness
v OBJECTIVES:
Ø Provides
an essential part of a strong foundation for building work
Ø Prevent
water moisture
Ø Concrete
is widely used for making architectural structures, foundations, brick/block walls, pavements,
bridges/overpasses,
motorways/roads, runways, parking
structures, dams,
pools/reservoirs, pipes, footings for gates, fences
and poles and even boats.
v SKILLS AND MANPOWER:
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
v TOOLS AND MATERIAL USED;
Ø Manila
thread
Ø Tape
measure
Ø Wheelbarrow
Ø Iron
scissors
Ø Spincers
Ø Concrete
mixer
Ø buckets
v INFLUENCE OF ENVIRONMENTAL
CONDITIONS.
Ø Weather:
dry and sunny.
Ø The
dry condition was very favorable and the work went smoothly without affecting
the block working process.
Ø The
sunny condition was also good and the walling work was not affected by the condition.
v SAFETY PRECAUTIONS.
Safety
tools used were gumboots, gloves, overcoats and helmets
Safety
precaution taken was
Ø wearing
safety boots, gumboots
Ø wearing
gloves to enable easy carrying of blocks.
Ø wearing
over coats and helmets
v CONCLUSION.
Ø All
works and activities were all performed and understood effectively.
Figure 6: Oversite Concrete Casting
WEEK
7 SUMMARY 14/08 - 19/08/2017
BLOCK WALL CONSTRUCTIONS
v INTRODUCTION:
Brick masonry building is the most
likely used type of structural system of Housing in many countries. More houses
are built using this system. Building a house without following the National
Standards of Earthquake design, the Masonry design standard and this Masonry
Construction guide could produce damage on the house. For our site the bond
used was stretcher bond.
v OBJECTIVES:
The
wall are used for protecting the occupant and their properties also as a
partitions, some time especially external wall can be used to transfer
loads(load bearing wall).
v SKILLS AND MAN POWER
Ø Foreman
Ø Cheap
labours
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour
v MATERIAL USED,
Ø Sand:
Ø Cement:
Ø Blocks
Ø Water
v TOOLS AND MACHINERY USED.
Ø Tools:
square rule, tape measure, plum bob, rope.
v PROCEDURES..
Ø
The
area was cleaned, all loose materials was removed
Ø Before
starting of block work, the area was washed with water.
Ø All
blocks was thoroughly
Wetted with water before
they were laid and tops of walls left from previous day work had to be
similarly wetted before the new work commenced.
Ø
Walls was built in stretcher bond
Ø An
axe was used for cutting the blocks when they needed to be cut also bolster could be used in preference to a trowel.
Ø All blocks was
laid on a full bed of mortar in perfectly horizontal courses, and all joints was set to be in perfect
vertical alignment and well filled by mortar the ends of the unit and then sliding into position against
its neighbor. Collar joints shall be filled by buttering the stretcher side
Ø Then
the setting out process begun by taking the blocks and marking by using blocks
where the walls are going to be built.
Ø Then
the mortar was prepared by mixing sand cement and water ratio(1:3) and by using
a plum bob the level of the blocks where checked to make sure they are leveled
and upright
v INFLUENCE OF ENVIRONMENTAL
CONDITIONS.
Ø Weather:
dry and sunny.
Ø The
dry condition was very favorable and the work went smoothly without affecting
the block working process.
Ø The
sunny condition was also good and the walling work was not affected by the condition.
v SAFETY PRECAUTIONS.
Safety
tools used were gumboots, gloves, overcoats and helmets
Safety
precaution taken was
Ø wearing
safety boots, gumboots
Ø Wearing
gloves to enable easy carrying of blocks.
Ø wearing
over coats and helmets
v CONCLUSION AND RECOMMENDATIONS.
Since
the blocks used were not of exactly same size they resulted in the bending of
walls and since they were using only floor plan without the section plan, there
were some walls that had to be brocken since they go higher than expected.
Example in the windows, 4 courses were built while they were supposed to be
three. This resulted to the breaking of walls to get three courses.
Therefore
during the blockworking it is recommended to use the blocks with exactly same
size and also to make a good use of section plan.
Figure 7: Block Wall Construction
WEEK
8 SUMMARY 21/08 - 25/08/2017:
FORMWORK PREPARATION AND
FIXING
v INTRODUCTION:
Formwork
for concrete work is described as a mould or box into which wet concrete can be
poured, compacted and vibrated so that it will flow and finally set to the
inner profile of the box or mould. The Ring beam formwork has the dimensions,
height 350mm, thickness 230mm and the slab formwork height was 150 mm,
dimensions were given on the plan.
A
column is the vertical member carrying the beam and floor loadings to the
foundation and is a compression member. The columns are made with reinforced
concrete; also columns are used to determine the exact position of walls,
stairs, and corridors and so on. Since concrete is strong in compression it may
be concluded that provided compressive strength of the concrete is not exceeded
no reinforcement would be required. For this condition to be true the following
conditions must exist:
v OBJECTIVE:
Formwork
is used to support structure temporarily and carry the wet concrete until when
it is hardened, it is also used to make the required concrete in a specific
shape and size for the time the concrete develops a sufficient strength to support itself.
v MATERIAL USED:
Ø Ply
wood/Marine board
Ø Timber.
Ø Nails
(3, 4 and 2.5 inches).
Ø Props
metals.
Ø Scaffold,
props.
Ø Buckets
for carrying concrete.
Ø Spades
for spreading the concrete.
v TOOLS AND MACHINE USED:
Ø Hand
saw.
Ø Tape
measure, Rope for lining, Circular saw , Claw hammer, Spirit level.
v PROCEDURES:
Ø The
all materials were prepared, timbers were planed to the required size and the
props were cut on site to the required size given on the drawing plan.
Ø The
soffits of the beams were constructed followed by the side of the beams
internally and the slabs soffits were constructed.
Ø The
props were placed together with scaffolding, 150mm to 200mm apart so as to
sustain the loads of slabs and beams.
Ø Lastly
the external side were placed per the drawing and supported per specification
as shown to the drawings.
v SKILLS AND MANPOWER:
Ø Foreman
Ø Cheap
labors
Ø Concrete
engineer
Ø Site
engineer
Ø Site
Engineers
Ø Foreman
Ø Trainees
Ø Skilled
labour,
v SAFETY PRECAUTIONS
The
students, workers, laborers and all peoples at the site were given safety gears to ensure that they are
safe. The construction site was a busy work environment so care was taken to
avoid run over by operating equipment and materials, also there was the first
aid kit available in case of an accident at the site
v INFLUENCE OF ENVIRONMENTAL CONDITIONS
During
construction of formwork the weather conditions were normal which allow the
carpenters and the laborers to work at the required time limit.
v CONCLUSIONS AND RECOMMENDATION.
The
work was performed well as per specification and completed at the required
time. And it was performed as an engineering work with, Quality, safety,
economic and within the required time.
Figure 8: Formwork and Concrete Casting
SPECIFIC REPORT
CONCRETING
Concrete is the heavy,
rough, building materials made from a mixture of aggregates, cement, sand, and
water, that can spread or poured out into moulds and that forms a stone- like
mass on hardening. It is strong in compression but weak in tension so that it
suppose to be reinforced so as to resist both, compression and tension,
concrete suppose to be consistency when applied and it always applied into
beams, slabs, and columns which both of them are in special form work to
prevent shrinkage of concrete.
Also Concrete is a composite construction
material composed primarily of aggregate, cement and water. There are many
formulations that have varied properties. The aggregate is generally coarse
gravel or crushed rocks such as limestone, or granite, along with a fine
aggregate such as sand. The cement, commonly Portland cement, and other
cementations materials such as fly ash and slag cement, serve as a binder for
the aggregate. Water is then mixed with this dry composite which enables it to
be shaped (typically poured) and then solidified and hardened into rock-hard
strength.
Slump test is the
measurement used to check consistency of the concrete by observing its degree
of shrinkage into the given slump cone, tools involved during slump test
includes, slump cone, tape measure, platform, concrete, iron rod
Figure
9: pouring of concrete
TYPES OF CONCRETE
MODERN CONCRETE
Most commonly,
regular concrete is created by mixing Portland cement with both an aggregate
and water-chemical mixtures. Often times, cement and concrete are incorrectly
interchanged: concrete is the hard, rock-like substance that is so frequently
seen in urbanized areas. Cement is an ingredient, the powder, used in the
creation of concrete. It is the most-produced material on Earth and will
continue to be so long as there is a need to create, rebuild, or improve
infrastructure.
HIGH-STRENGTH CONCRETE
High-strength concrete is different from
normal-strength concrete in the amount of force it can resist without breaking.
The American Concrete Institute differentiates high-strength from
normal-strength at a compressive strength of over 6,000 psi (pounds square
inch). In addition to varying the proportions of the materials used in
normal-strength concrete, silica fume is added to the mixture in order to
strengthen the bond between the cement and the aggregate. However, this
admixture causes the cement to hydrate much faster, meaning that it dries
quicker than usual. In order to keep consistent the balance between workability
and strength, a superplasticizer is added to high-strength concrete. This slows
down the chemical reaction between the cement and water, allowing for workers
to place the concrete at a more effective pace
HIGH-PERFORMANCE CONCRETE (HPC)
High-performance concrete, in contrast to
high-strength concrete, is not necessarily known for its compressive
resistance. While high-performance concrete can include a high compressive
strength, other characteristics used to define “high performance” are the ease
of placement without affecting strength, long-term mechanical properties,
toughness, and longevity in various weather conditions among others
ULTRA HIGH-PERFORMANCE CONCRETE
This type of concrete is more often than not pre-mixed
in bags because of the numerous ingredients needed to make it. It includes
Portland cement, silica fume, quartz flour, and fine silica sand. However,
high-range water reducers, water, and other steel or organic fibers are used to
increase the strength of the mixture. Ultra-high performance concrete is
particularly durable because of the combination of fine powders. Other types of
concrete normally need a steel rebar or reinforcing to retain the intended
structure, but UHPC is generally self-placing in addition to its incredible
compressive strength of up to 29,000 psi. Its post-cracking longevity is
one of UHPC’s strong points because even after this concrete cracks, it still
is able to maintain structural integrity with an impressive tensile strength
STAMPED CONCRETE
Stamped concrete
is another type of concrete that is very commonly used. Often seen in parking
lots, pavements, or other like high-traffic areas, stamped concrete has more of
an architectural application. Once concrete has been laid, a kind of mold can
be placed on top of, or stamped, onto the hardening concrete to create the
appearance of natural stone. Once the floor has been hardened, it will likely
be sealed to increase the longevity of the dried mixture.
SELF-CONSOLIDATING CONCRETE
Normally, concrete requires a mechanical vibration
while being set in order to release excess air that may be in the mixture.
Self-consolidating concrete eliminates the need for mechanical consolidation
(the vibrations) mainly through its malleable viscosity. Being able to control the
flowability and stability, as achieved by using high-range-water-reducing
admixtures, allows concrete to be placed quicker. Not only does this save time,
but because there is no need for the mechanical consolidation,
self-consolidating concrete saves labor, saves money, and makes it easier for
workers to fill restricted or hard-to-reach areas.
SHOTCRETE
Invented by taxidermist, Carl Akeley in 1907, the
initial dry method for placing shotcrete was by using a compressed air nozzle
to shoot dry mix and injecting water through a separate hose at the head of the
nozzle while the dry material is hurled toward the wall. The wet-mix shotcrete
was developed later in the 1950’s and is only slightly different than the
dry-mix shotcrete wherein dry-mix shotcrete involves the continuous feeding of
a hopper through which dry mix would shoot through a nozzle and mix at the
point of exit. Wet-mix shotcrete, however, involves the use of pre-mixed
concrete. The concrete has already been prepared and therefore only involves
one pump. The upside to using wet-mix shotcrete is that dry-mix shotcrete
creates more waste (excess powder that falls to the floor), more rebound off
the wall, and wet-mix shotcrete can place a larger quantity in a smaller amount
of time.
LIMECRETE
Also known as
lime concrete, limecrete is a type of concrete where instead of using cement in
the mix, lime is replaced. Doing so has certain benefits environmentally and
health-wise. Environmentally, lime absorbs carbon dioxide as it sets and allows
natural products like wood, straw, and hemp to be used as fibers without fear
of composting or deterioration since limecrete controls moisture. In terms of
health, lime plaster draws moisture out from inside which means that humidity
control is more regulated, resulting in mold growth prevention. Furthermore,
limewash and lime plasters are non-toxic so they do not contribute to air
pollution inside like other paints would
OBJECTIVE:
Concrete
is widely used for making architectural structures, foundations, brick/block
walls, pavements, bridges/overpasses, motorways/roads, runways, parking
structures, dams, pools/reservoirs, pipes, footings for gates, fences and poles
and even boats.
MATERIALS
AND TOOLS USED;
Materials,
Ø Aggregates
Ø Sand
Ø Cement
Ø Water
CEMENT
The cement delivered on site was then
stored in water proofed shed, and well prevented from contamination of any sort
or from any cause. It’s well in doubt that the hardened cement due to poor
stored shall never be used in any building
Construct. Also the different types delivered to site,
were kept separate in storage and that was mixed together in the production of
structural concrete.
WATER
Water is one among the composition of
concrete, water helps in dehydration process and also provision good and strong
bond of any structural consisting of cement and sand.
SAND
Sand
as a naturally occurring granular material which is composed of freely divided
rock and mineral particles are known to be formed by the weathering of rocks.
The types of sand used are either
ü Pit
sand
ü River
sand or both
AGGREGATES
Aggregates were well cleaned and free
from dust and they were of quality and nature required. The aggregate used were
coarse aggregates of;
Ø 10mm
max. size, graded, for all “fine” concrete
Ø 20mm
max. size, graded, for all reinforced concrete in beams and for walls and slabs
not greater than 400mm thick.
Ø 40mm
max. size ,graded, for all reinforced concrete walls and slabs in excess of
400mm thick and mass concrete members
Figure 10: POURING OF CONCRETE
CONCRETE
PRODUCTION:
Ø Concrete
production is the process of mixing together the various ingredients—water,
aggregate, cement, and any additives—to produce concrete. Concrete production
is time-sensitive. Once the ingredients are mixed, workers must put the
concrete in place before it hardens. In modern usage, most concrete production
takes place in a large type of industrial facility called a concrete
plant, or often a batch plant.
Ø In
general usage, concrete plants come in two main types, ready mix plants and
central mix plants. A ready mix plant mixes all the ingredients except water,
while a central mix plant mixes all the ingredients including water. A central
mix plant offers more accurate control of the concrete quality through better
measurements of the amount of water added, but must be placed closer to the
work site where the concrete will be used, since hydration begins at the plant.
Ø A
concrete plant consists of large storage hoppers for various reactive
ingredients like cement, storage for bulk ingredients like aggregate and water,
mechanisms for the addition of various additives and amendments, machinery to
accurately weigh, move, and mix some or all of those ingredients, and
facilities to dispense the mixed concrete, often to a concrete
mixer truck.
Ø Modern
concrete is usually prepared as a viscous fluid, so that it may be poured into
forms, which are containers erected in the field to give the concrete its
desired shape. Concrete formwork can be prepared in several ways, such
as Slip forming and Steel plate construction. Alternatively,
concrete can be mixed into dryer, non-fluid forms and used in factory settings
to manufacture Precast concrete products.
Ø A
wide variety of equipment is used for processing concrete, from hand tools to
heavy industrial machinery. Whichever equipment builders use, however, the
objective is to produce the desired building material; ingredients must be
properly mixed, placed, shaped, and retained within time constraints. Any
interruption in pouring the concrete can cause the initially placed material to
begin to set before the next batch is added on top. This creates a horizontal
plane of weakness called a cold
joint between the two batches, Once the mix is where it should
be, the curing process must be controlled to ensure that the concrete attains
the desired attributes. During concrete preparation, various technical details
may affect the quality and nature of the product.
Ø When
initially mixed, Portland cement and water rapidly form a gel of tangled
chains of interlocking crystals, and components of the gel continue to react
over time. Initially the gel is fluid, which improves workability and aids in
placement of the material, but as the concrete sets, the chains of crystals
join into a rigid structure, counteracting the fluidity of the gel and fixing
the particles of aggregate in place. During curing, the cement continues to
react with the residual water in a process of hydration. In properly
formulated concrete, once this curing process has terminated the product has
the desired physical and chemical properties. Among the qualities
typically desired are mechanical strength, low moisture permeability, and
chemical and volumetric stability.
BATCHING AND
MIXING CONCRETE
Mixing concrete is simply defined as the
"complete blending of the materials which are required for the production
of a homogeneous concrete". This can vary from hand to machine mixing,
with machine mixing being the most common.
However, no successful mixture can be achieved
without the proper batching of all materials. Batching is the
"process of weighing or volumetrically measuring and introducing into the
mixer the ingredients for a batch of concrete". Quality assurance,
suitable arrangement of materials and equipment, and correct weighing of the
materials are the essential steps that must be completed before any mixing
takes place.
The types and volume of materials, the mix design,
and the end result (i.e. strength) are normally provided in the design
specifications. The design specifications must be consulted before any batching
or mixing takes place.
COMPONENTS
OF MIXING
There
are many components of mixing that need to be considered in order to
ensure that a uniform concrete mixture can be achieved. Location, shape and
angle of the mixing blades, shape of the mixing chamber, speed of rotation, and
horsepower must all be taken into account. It is paramount that each batch is
consistently mixed to design specifications so the concrete’s final strength is
not compromised.
CLASSIFICATIONS
OF MIXERS
There are essentially three classifications of
mixers:
Ø
the drum mixer,
Ø
pan mixer, and
Ø
Continuous mixer.
Each of these mixers can be further classified as
batched or continuous, free-falling or forced movement, and stationary or portable.
MIXING
TIME
Once the appropriate mixer has been chosen, it is necessary to determine the
mixing time. This is the duration of time it takes to mix concrete, once
the mixer is fully charged with all the materials. Charging is an important
step because it gives the materials an opportunity to pre-blend. The type
and condition of the mixer, speed of rotation, size of the charge, and
nature of the materials all determine the correct mixing time. The mixing time
is not
standard for each batch. For example, a drum mixer with a small diameter creates a greater velocity than a drum mixer with a large diameter, therefore, the mixing time would be decreased. However, if the goal is stiffer concrete, a longer mixing time is required.
standard for each batch. For example, a drum mixer with a small diameter creates a greater velocity than a drum mixer with a large diameter, therefore, the mixing time would be decreased. However, if the goal is stiffer concrete, a longer mixing time is required.
Figure 11: CONCRETE PRODUCTION
MECHANICAL MIXING
This process was done by using tilting
drum mixers.
Ø Sand,
cement, aggregates and water was measured in volume then taken in the mixing
machine, the drum rotated on an inclined axis during mixing process and on a
titled axis for discharging. Three position were used , which were;
(a) Charging
position, example loading cement, sand and aggregates.
(b) Mixing
position
(c) Discharging
position
Ø At
the batching plant slump test is carried out on each mix produced. The 4 cubes
is casted then cured for seven days to obtain their strength then they are
taken to the laboratory for strength test.
Ø The
principal basis of control is comparison of the results of the compression
cubes tests at 28 days. The cubes are
compressed up to when they got cracks at the moment of failure the forced used
value was read Compression test were
carried out at 7 days and adjustment made in volume of the main control method
outlined above. Cube test results were examined individually, then the average
value of each cube was calculated, standard deviation and mean accepted only if
strength of each set calculated.
Ø We
used buckets and wheelbarrows as means of transportation of fresh concrete from
one point to another, whereby we washed the buckets so as to make sure that the
concrete is well carried and not contaminated with any dust
CURING:
Concrete must be kept moist during
curing in order to achieve optimal strength and durability. During
curing hydration occurs, allowing calcium-silicate hydrate to form
Ø Hydration
and hardening of concrete during the first three days is critical. Abnormally
fast drying and shrinkage due to factors such as evaporation from wind during
placement may lead to increased tensile stresses at a time when it has not yet
gained sufficient strength, resulting in greater shrinkage cracking. The early
strength of the concrete can be increased if it is kept damp during the curing
process. Minimizing stress prior to curing minimizes cracking. High-early-strength
concrete is designed to hydrate faster, often by increased use of cement that
increases shrinkage and cracking. The strength of concrete changes (increases)
for up to three years. It depends on cross-section dimension of elements and
conditions of structure exploitation. Addition of short-cut polymer fibers
can improve (reduce) shrinkage-induced stresses during curing and increase
early and ultimate compression strength.
Ø Properly
curing concrete leads to increased strength and lower permeability and avoids
cracking where the surface dries out prematurely. Care must also be taken to
avoid freezing or overheating due to the exothermic setting of
cement. Improper curing can cause scaling, reduced strength,
poor abrasion resistance and cracking.
TECHNIQUE
During the curing period, concrete is
ideally maintained at controlled temperature and humidity. To ensure full
hydration during curing, concrete slabs are often sprayed with "curing
compounds" that create a water-retaining film over the concrete. Typical
films are made of wax or related hydrophobic compounds. After the concrete is
sufficiently cured, the film is allowed to abrade from the concrete through
normal use.
Traditional conditions for curing
involve by spraying or ponding the concrete surface with water. The adjacent
picture shows one of many ways to achieve this, ponding – submerging
setting concrete in water and wrapping in plastic to prevent dehydration.
Additional common curing methods include wet burlap and plastic sheeting
covering the fresh concrete.
For higher-strength
applications, accelerated curing techniques may be applied to the
concrete. One common technique involves heating the poured concrete with steam,
which serves to both keep it damp and raise the temperature, so that the hydration
process proceeds more quickly and more thoroughly.
PROPERTIES OF CONCRETE
GRADES OF CONCRETE
Concrete is known by its grade
which is designated as M15, M20 etc. in which letter M refers to concrete mix
and number 15, 20 denotes the specified compressive strength (fck) of 150mm cube at 28 days, expressed in N/mm2.
Thus, concrete is known by its compressive
strength. M20 and M25 are the most common grades of concrete, and higher grades
of concrete should be used for severe, very severe and extreme environments.
COMPRESSIVE
STRENGTH OF CONCRETE
Like load, the strength of the concrete is also a
quality which varies considerably for the same concrete mix. Therefore, a
single representative value, known as characteristic strength is used.
TENSILE STRENGTH OF CONCRETE
The estimate of flexural tensile strength or the
modulus of rupture or the cracking strength of concrete from cube compressive
strength is obtained by the relations
fcr = 0.7 fck N/mm2. The tensile strength of concrete in direct tension
is obtained experimentally by split cylinder. It varies from 1/8 to 1/12 of
cube compressive strength.
CREEP IN CONCRETE
Creep is defined as the plastic deformation under
sustained load. Creep strain depends primarily on the duration of sustained
loading. According to the code, the value of the ultimate creep coefficient is
taken as 1.6 at 28 days of loading.
SHRINKAGE OF CONCRETE
The property of diminishing in volume during the
process of drying and hardening is termed Shrinkage. It depends mainly on the duration
of exposure. If this strain is prevented, it produces tensile stress in the
concrete and hence concrete develops cracks.
DURABILITY OF CONCRETE
Durability of concrete is its ability to resist its
disintegration and decay. One of the chief characteristics influencing
durability of concrete is its permeability to increase of water and other
potentially deleterious materials.The desired low permeability in concrete is
achieved by having adequate cement, sufficient low water/cement ratio, by
ensuring full compaction of concrete and by adequate curing.
WORKABILITY OF CONCRETE
Ø Workability is the ability of a fresh (plastic) concrete mix
to fill the form/mold properly with the desired work (vibration) and without
reducing the concrete's quality. Workability depends on water content,
aggregate (shape and size distribution), cementitious content and age (level
of hydration) and can be modified by adding chemical admixtures, like
super plasticizer. Raising the water content or adding chemical admixtures
increases concrete workability. Excessive water leads to increased bleeding
or segregation of aggregates (when the cement and aggregates start to
separate), with the resulting concrete having reduced quality.
Ø The use of an aggregate blend with an undesirable
gradation can result in a very harsh mix design with a very low slump,
which cannot readily be made more workable by addition of reasonable amounts of
water. An undesirable gradation can mean using a large aggregate that is too
large for the size of the formwork, or which has too few smaller aggregate
grades to serve to fill the gaps between the larger grades, or using too little
or too much sand for the same reason, or using too little water, or too much
cement, or even using jagged crushed stone instead of smoother round aggregate
such as pebbles.
Ø Any combination of these factors and others may result
in a mix which is too harsh, i.e., which does not flow or spread out smoothly,
is difficult to get into the formwork, and which is difficult to surface finish
RECOMANDATION.
Ø The
cement must be checked whether it was manufactured recently.
Ø The
ratio should be controlled while mixing
Ø The
workers should have safety gears for their health and safety.
Ø The
pegs and marks exposed should be followed while leveling the concrete.
Ø The
selection of the equipment should match the work to be done
Ø Concrete
should be well compacted.
GENERAL CONCLUSION:
Practical
training started 30 AUGUST 2018 and ended 04 SEPTEMBER 2018, those eight weeks
were good and enjoyable. Special thanks to NEW AGE CONSTRUCTION COMPANY for
caring, support, encouragement even using their funds to facilitate learning
during the entire practical training period
Practical
training is very important to students especially for quantity surveying
students because to learn theory only is not enough to be competent to be a
civil engineer.PT is also important because it makes the student to interact
between engineers, technicians and other potential people helpful in their
carrier. There were problems met at site that won’t be taught in class, so how
they got solved students learn from it. There are people especially in site
that sometime to interact with the
0 Comments