PREFERENCE
The practical training is carried out for eight
weeks at the end of each academic year by the scholars. Where by the university
supervisors visits the trainees in site and asses them
The main objective of this practical training is to
provide the practical knowledge of the lessons learnt in class. This ultimately
helps the university to produce competent professionals.
ABSTRACT
This report concerns about the first practical
training of the academic year 2015/2016 on the proposed construction of a CITY
LOGDE hotel at Ilala municipality in Dar es salaam, Tanzania
This is a general report of the practical training
which includes hand written weekly log books and typed weekly summary of the
week`s main job.
And it also covers brief explanations upon the
project itself showing the involved parties, the organization of the contractor
company and a sample of the equipment and technologies used in performing the
project.
ACKNOWLEDGEMENT
Firstly, with my exceedingly humbled heart, I would
like first to thank God almighty for giving me the strength to successively
conduct my first practical training.
Secondly, I would like to appreciate and give thanks
to the following individuals according to the roles played by each one of them
upon making my successive completion of the practical training;
ü ENG.
ABDALLAH RASHID (the site engineer for the project) ENG. RAMADHAN YAKINI thee
assistant site engineer. For training me practically in site
ü My
fellow PT trainees, for giving the team work support needed in performing activities.
Last but not least, I
would like to thank the staff members of department of structural and
construction engineering for providing the required knowledge of different
activities in my faculty.
CHAPTER ONE (1)
GENERAL
INTRODUCTION OF THE FIRST PRACTICAL TRAINING (PT 1)
1.0 Introduction
This chapter comprises of brief details about the
project which includes the names of the client, architect, quantity surveyor,
the civil and structural engineer of the project, electrical and mechanical
sub-contractors and the main contractor. This chapter also covers a brief
description of the profile of the company which I was doing the practical
training along with its organization system. And finally the summary of the
project which includes the location of the site, the estimated time of
completion, site organization along with the techniques and equipment used in
this project.
1.1 About the
project
The project details are as follows;
CLIENT:
CITY LODGE HOTEL GROUP TANZANIA LTD
ARCHITECT:
PDW ARCHITECTS LTD
QUANTITY
SURVEYOR: CQS SERVICES LTD
CIVIL
& STRUCTURAL ENGINEER: HOWARD HUMPHREYS (T) LTD
ELECTRICAL
& MECHANICAL ENGINEER: DESIGN INCORPORATED LTD AND
KIMPHIL KONSULT (T) LTD
MAIN
CONTRACTOR: ESTIM CONSTRUCTION COMPANY LTD
1.2 About the
company
The company which I performed my first practical
training is called ESTIM Construction Company Limited. The company is one of
the first class construction companies in Tanzania. The head quarter of the
company is at Mwenge in Dar es salaam, Tanzania.
In the past few years the company has been
undertaking some of the most large construction projects in the country, for
example; the 45 storey building (PSPF TOWERS) which is currently the tallest
building in East Africa.
1.3
The organization system of the Estim construction company
The figure below is a chart of Estim construction
company organization.
1.4
Summary of the project
Location;
The project site is located at Posta near the kisutu
magistrate court in Dar es salaam, Tanzania.
Aim of the project;
The aim of the project is to construct a commercial
building which will used as a hotel called the CITY LODGE HOTEL which is going
to be constructed for twenty (20) months.
The site organization structure;
The project engineer was the head of the project,
the site engineer reported to the project engineer, the project manager, safety
department and the foremen all reported either to the site engineer or to the
project engineer.
The chart below shows the organization structure the
site:
Techniques and equipment’s used in the site;
Here are some of the equipment used in site
ü Crane for lifting heavy loads
ü Excavator for digging
ü Mobile concrete pump
ü Poker vibrator, for compacting concrete
ü Damp level and leveling staff
ü Spray paints for putting marks
ü Tampering rammer, for compacting the soil
ü Security cameras (CCTV) to monitor the security in site
ü Crane for lifting heavy loads
ü Excavator for digging
ü Mobile concrete pump
ü Poker vibrator, for compacting concrete
ü Damp level and leveling staff
ü Spray paints for putting marks
ü Tampering rammer, for compacting the soil
ü Security cameras (CCTV) to monitor the security in site
CHAPTER TWO (2)
THE WEEKLY SUMMARIES
2.0
Introduction
This chapter contains a brief descriptions of the main
jobs done in each week for eight (8) weeks which covers the following;
ü A
brief meaning or definition of the work.
ü The skills and man power used in the particular work.
ü The time required to perform the work.
ü The materials used along with their sources and origin.
ü Tools and machineries used to do the particular work.
ü The procedures followed in performing the work.
ü Effects of the environmental conditions to the work.
ü Safety precautions observed by the workers in performing the job.
ü Conclusions as well as recommendations regarding the main job of each week.
ü A few pictures concerning the week`s main job.
ü The attached log book of each week.
ü The skills and man power used in the particular work.
ü The time required to perform the work.
ü The materials used along with their sources and origin.
ü Tools and machineries used to do the particular work.
ü The procedures followed in performing the work.
ü Effects of the environmental conditions to the work.
ü Safety precautions observed by the workers in performing the job.
ü Conclusions as well as recommendations regarding the main job of each week.
ü A few pictures concerning the week`s main job.
ü The attached log book of each week.
2.1.0
WEEKLY SUMMARY 1 FROM 08TH/8/2016 TO 13TH/8/2016
FORMWORKS
FOR STAIRS OF THE BASEMENT
2.1.1
Introduction:
Formworks these are temporary molds in which
concrete is poured into it and left for some time until it regains its strength
and the desired shape of a structure. During the construction of formworks of
the stairs the formworks used were of two (2) types; the ones which are made
out of plywood and steel formworks.
2.1.2
Skills and manpower
The task was carried out by the following kinds of
workers;
ü Civil
engineer
ü Technician
ü Unskilled
labors
ü Trainees
(PT students)
2.1.3
The time required
This work was required to be accomplished in a
single day, and it took us about six (6) hours. Hence it was finished within
the required time.
2.1.4
Materials used, their sources and origin
Material used in this task are;
ü Ply
woods 20mm thick
ü Timber,
4×2 inch wood and 6×2 inch wood
ü Scaffolds
Sources and origin of the materials;
ü The
ply woods and the metallic scaffolds are imported.
ü Timber
are locally sourced.
2.1.4
Tools and machinery used
Here is a list of the tools used in this job;
ü Bolts
ü Spirit
level
ü Nails
and hammer
ü A
circular saw machine
ü A
tape measure
ü 20mm
thick ply wood
ü 4×2
inch wood
ü 6×2
inch wood
2.1.5
Procedures
ü Firstly,
the surveyor placed the markings which should be observed by the labors who are
going to construct the formworks.
ü Secondly, all the required materials which are to be used in the construction of the formworks are gathered.
ü Thirdly, the plywood as well as the timber are cut into the required dimensions so that they can be well fitted.
ü Finally, the plywood along with the timber are fixed in position following the order instructed in the structural drawings of a particular stair, and they are held in position with the help of the scaffolds
ü Secondly, all the required materials which are to be used in the construction of the formworks are gathered.
ü Thirdly, the plywood as well as the timber are cut into the required dimensions so that they can be well fitted.
ü Finally, the plywood along with the timber are fixed in position following the order instructed in the structural drawings of a particular stair, and they are held in position with the help of the scaffolds
2.1.6
Influence of environmental conditions
The weather condition was sunny hence the work
proceeded as planned.
2.1.7
Safety conditions
To ensure the safety of the people involved in this
work, the workers wore protective gears such as;
ü Helmet
ü Boots
ü Gloves
ü Boots
ü Overall
ü Reflectors
2.1.8
Conclusion and recommendations
Generally, the work proceeded as planned since the
required dimensions of the stairs were obtained.
2.2.0
WEEKLY SUMMARY TWO (2) FROM 15TH/8/2016 TO 20TH/08/2016
STEEL FIXATION ON THE
GROUND FLOOR
2.2.1
Introduction
It is the process of cutting, aligning and joining
the reinforcement bars in accordance to the structural drawing details.
2.2.2 Skills and manpower
This task was performed by the following people;
ü Civil
engineer
ü Foremen
ü Unskilled
labors
ü Trainees
(PT students)
2.2.3
Time required.
This work was required to be completed in three
days, but unfortunately the work took almost five days. This is because when
the initially done work was supervised by the consultant it was noted that some
parts were incorrectly fixed. This took us an addition of two more days to
amend the errors which occurred.
2.2.4
Materials used, their sources and origin
The materials used in this task were;
ü High
tensile steels of different diameters and length
ü Binding
wires
Some of the tensile steels were imported for example
the Y 32 steel
2.2.5
Tools and machinery used
ü Pincer.
ü Tape
measure.
ü Bar
benders.
ü Binding
wires.
2.2.6
Procedures
ü All
materials indicated in the structural drawing for the slab were gathered.
ü The
tensile steels were cut and bended as indicated in the bar schedule.
ü The
bottom one steels were placed at a spacing of 200mm from one another. And the
bottom two steels were placed on top of them facing the other direction but
just as the bottom one steels they were also placed at a spacing of 200mm and
then tied together by binding wires.
ü The
chair bars were placed on top of bottom one and two rebar. The chair bars were
placed at an approximate distance of one meter apart.
ü The
top two steels were placed on top of the chair bars at a spacing of 200mm from
one another then tied onto them by the means of a binding wire.
ü Finally,
the top one steels were placed on top of the top two at a spacing of 200 mm
from each other.
2.2.7
Influence of environmental conditions
The weather conditions of this day was sunny hence
the work proceeded without any delaying problem.
2.2.8
Safety precautions
To ensure safety for the workers, the labors who
participated in this job were required to wear protective gears such as;
ü Helmet
ü Gloves
ü Safety
boots
ü Overall
2.2.9
Conclusions and recommendations
Conclusion;
Generally, although this work was delayed the labors
eventually achieved the required specifications of the slab reinforcements as
indicated in the structural drawings.
2.3.0
WEEKLY SUMMARY THREE (3) FROM 22ND/08/2016 TO 27TH/08/2016
INSTALLING
FOR PIPES AND DUCTS FOR ELECTRICAL AND WATER SERVICES
2.3.1
Introduction
Pipes installation it is simply a process of placing
pipes within the slab and column reinforcements in order for them to serve both
electrical and water services.
2.3.2
Skills and manpower
For the work of
electrical services pipes;
ü Foreman.
ü Technicians.
ü Trainees (PT students).
ü Trainees (PT students).
2.3.3
Time used
The time required to do
this job was 6 hours. Unfortunately, the job took about eight hours due to the
rain.
2.3.4
Materials used, their sources and origin
The basic materials
used in this task were;
ü PVC
plastic pipes.
ü Glue.
2.3.5
Tools and machinery used
ü Electric
heater to help in bending the pipes.
ü Junction
connectors.
ü Saw
for cutting the pipes.
2.3.6
Procedures
ü The
ducts are placed on the floor slab
ü The
pathway of the pipes are marked by the means of the spray paints
2.3.7
Influence of environmental conditions
The weather in this day
was rainy, hence it slowed down the work.
2.3.8
Safety precautions
To ensure the safety
the workers wore;
ü Helmet
ü Safety
boots
ü Overall
ü Gloves
2.3.9
Conclusion and recommendations
Although the work was
delayed by the rain, it was accurately finished.
2.4.0
WEEKLY SUMMARY FOUR (4) FROM 29TH/08/2016 TO 31ST/08/2016
ERECTION OF FORMWORK FOR COLUMNS
2.4.1
Introduction
Formworks are simply temporary molds which concrete
is poured into it and left for some time in order for it to acquire its
strength and the required shape of a structure.
2.4.2
Skills and manpower
The manpower which participated in this work was;
ü Foreman
ü Unskilled
labors
ü Trainees.
2.4.3
Time required.
The time required to perform the task is eight (8)
hours.
2.4.4
Materials used, their sources and origin
ü Ply
wood
ü Diesel
oil
ü Timber
ü Scaffolds
2.4.5
Tools and machinery used
ü Crane
ü Plumb
bob
ü Spirit
level
ü Bolts
ü Circular
saw for cutting timber
ü Tape
measure
2.4.6
Procedures
ü The
surveyor placed the marks which were to be followed by the labors
ü The
materials to be needed were brought nearby, some were carried by the crane.
ü The
formworks were erected around those marks and attached together by using bolts.
Note the formworks are separated from the reinforcements by a 40mm thick space
bar.
ü Then
a plumb bob was used to check the verticality of the formworks.
ü Finally,
the vertical formworks were firmly fitted by using scaffolds and bracings.
2.4.7
Influence of the environmental conditions
The work was done on a sunny day, hence the weather
conditions had insignificant effects on the job.
2.4.8
Safety precautions
Safety gears were provided to ensure no any injuries
occur. The safety gears were;
ü Helmet
ü Boots
ü Gloves
ü Reflectors
2.4.9
Conclusion and recommendations
The job of erection of formworks was in finished in
time.
2.5.0 WEEKLY SUMMARY FIVE (5) FOR 5TH/09/2016 TO 10TH/09/2016
CURING OF THE GROUND FLOOR SLAB,
COLUMNS AND SHEAR WALLS
2.5.1
Introduction
Curing of concrete is process of providing adequate
moisture, temperature and time to allow the concrete to achieve the desired
properties for the intended use. Usually the curing of a structure starts a day
after the concrete is poured and the process is carried on for about four
weeks.
2.5.2
Skills and manpower
Due to the nature of the work this work is done by
only one (1) person.
2.5.3
Time required
The time required to perform this task is three (3)
hours
2.5.4
Materials used, their sources and origin
ü Clean
water.
ü Sacks
to help in retaining water for a long time.
2.5.5
Tools and machinery used
ü Pump.
ü Water
pipes.
2.5.6
Procedures
ü The
formworks are removed from the columns and shear walls.
ü The
structures which are to be cured are covered properly with sacks
ü The
structures to be cured are then watered using clean water.
2.5.7
Influence of environmental conditions
Since this activity is required to be done almost
all in days of construction, in sunny weather this activity is carried out, but
in rainy days this activity is not done since the structures to be cured will
already be wet.
2.5.8
Safety precautions
In order to ensure safety the worker wears
Ø Gum
boots
Ø Helmet
Ø Hand
gloves
Ø Reflector
Ø Overall
2.5.9
Conclusion.
The curing work is very essential so as to enable
the concrete structure to attain its maximum strength.
2.6.0
WEEKLY SUMMARY SIX (6) FROM 12TH/09/2016 TO 17TH/09/2016
CONCRETE POURING, COMPACTION AND
SLUMP TESTS
2.6.1
Introduction
Concrete pouring is done after the fixation of the
reinforcements and the erection of the formworks around the structure. During
the pouring of concrete slump test is conducted as well as the preparation of
cubes is done.
A slump test, is a method of assessing the freshness
of concrete by indirectly checking the amount of water that is mixed in the
concrete.
2.6.2
Skills and manpower
The task of concrete requires the following man
power
Civil
engineer
ü Foreman
ü Unskilled labors
ü Foreman
ü Unskilled labors
The task of slump test and preparation of cubes is
done by only one person.
2.6.3
Time required
The time required to complete this task was three hours.
2.6.4
Materials used, their sources and origin
ü Concrete
is prepared in the company`s batch plant and carried to the site by means of
the special trucks.
2.6.5
Tools and machineries used
The tools used in pouring of concrete are;
ü Poker
vibrator
ü Metallic pegs
ü A mobile concrete pump
ü Power floats
The tools used in slump test are;
ü A slump cone
ü A slump road
ü A tape measure
ü Metallic pegs
ü A mobile concrete pump
ü Power floats
The tools used in slump test are;
ü A slump cone
ü A slump road
ü A tape measure
2.6.6
Procedures
Procedures for concrete pouring;
ü The adjustable metallic pegs are such a way that its height is equal to the required thickness of slab by the help of a surveyor.
ü The concrete carrier truck is stationed in such a way that it pours concrete into the mobile concrete pump.
ü The concrete is poured onto the slab carefully not to exceed the height of the metallic pegs
ü When the already poured concrete hardens a little bit, it is smoothen by the power float so as to get an elegant finish of the slab.
Note: they concrete grade of all vertical structures example columns was grade 40 and for all horizontal structures was grade 30.
Procedures for slump tests;
ü The slump tests is carried out simultaneously with the pouring of concrete.
ü The slump test is carried out for the concrete carried in each truck, so as to know if the concrete is fit for usage or not.
ü The concrete is placed in the slump cone which is 300mm tall
ü Then the cone is removed vertically upward, then the final height of the concrete is subtracted from the initial height which 300mm to obtain the change in height.
ü If the concrete passes the slump test, then it will be used but if not it will be rejected’
ü The adjustable metallic pegs are such a way that its height is equal to the required thickness of slab by the help of a surveyor.
ü The concrete carrier truck is stationed in such a way that it pours concrete into the mobile concrete pump.
ü The concrete is poured onto the slab carefully not to exceed the height of the metallic pegs
ü When the already poured concrete hardens a little bit, it is smoothen by the power float so as to get an elegant finish of the slab.
Note: they concrete grade of all vertical structures example columns was grade 40 and for all horizontal structures was grade 30.
Procedures for slump tests;
ü The slump tests is carried out simultaneously with the pouring of concrete.
ü The slump test is carried out for the concrete carried in each truck, so as to know if the concrete is fit for usage or not.
ü The concrete is placed in the slump cone which is 300mm tall
ü Then the cone is removed vertically upward, then the final height of the concrete is subtracted from the initial height which 300mm to obtain the change in height.
ü If the concrete passes the slump test, then it will be used but if not it will be rejected’
Note: The
change in height obtained from the slump test can be group into three
categories;
ü True
slump which ranges from 0mm to 80mm
Fit
for usage when the concrete is poured by using buckets
ü Shear
slump which ranges from 80mm to 150mm
Fit
for usage when the concrete is poured by using a pump
ü Collapse
slump ranges from 150mm and above
Not
fit for usage at all
2.6.7
Influence of the environmental conditions
The weather conditions were favorable, and did not
cause any significant effects on the job.
2.6.8
Safety precautions
To ensure the safety of the workers wore;
ü Helmets
ü Gloves
ü Gum
boots
ü Reflectors
2.6.9
Conclusion
All in all, the work proceeded as planned.
2.7.0
WEEKLY SUMMARY SEVEN (7) FROM 19TH/09/2016 TO 24TH/09/2016
EXCAVATION
OF TRENCHES AND MATERIAL INSTALLATION FOR FRENCH DRAINAGE SYSTEM
2.7.1
Introduction
A French drain is a trench filled with gravel,
perforated pipes all wrapped in a geotextile material so as to help to redirect
water (both surface water and ground water) away from the area. In the case of
the site I was in the French drainage system was installed to redirect water
away from the foundation walls.
A perforated pipe is a pipe with small slots through
which water can pass through them
2.7.2 Skills and manpower
The manpower involved in this task were as follows;
ü A
surveyor: who helped at getting the required level and slope of the trench.
ü Unskilled
labours
ü A
foreman
ü A
site engineer
2.7.3
Time required
The time required to complete this task was four (4)
days.
2.7.4
Materials used, their sources and origin
ü Gravels
ü Geo
textiles
ü Perforated
PVC pipes
2.7.5
Tools and machinery used
ü Shovels
ü A
damp level
ü A
levelling staff
ü A
tape measure
2.7.6 Procedures
ü A
500mm wide trench is dug at approximate distance of 1 meter away from the
foundation wall.
ü The
required slope of the trenches is obtained under a supervision of a surveyor.
ü The
geo textiles are placed inside the trenches followed by the gravels on top of
it.
ü The
perforated pipes are placed onto the gravels.
ü Then
the pipes are covered by gravels again on top then the system is covered with
in the geo textile.
ü After
installing the system the soil was backfilled and it was well compacted by the
use of a tampering rammer and a roller.
Note: the purpose of the geo textile and gravels is
to limit the entrance of sand or soil inside the perforated pipes.
2.7.7
Influence of the environmental conditions
The weather was good hence the work proceeded as
planned.
2.7.8
Safety precautions taken.
To ensure the safety of the workers they each wore
the following protective gears;
ü Helmet
ü Boots
ü Overall
ü Gloves
2.7.9
Conclusion
The work was well completed without any problem.
2.8.0
WEEKLY SUMMARY EIGHT (8) FROM 26TH/09/2016 TO 1ST/10/2016
STEEL FIXING OF THE COLUMNS IN THE
SECOND FLOOR
2.8.1
Introduction
It is the process of cutting, aligning and joining
the reinforcement bars in accordance to the structural drawing details. The
steel fixing of columns
2.8.2 Skills and manpower
The task was done by the following set of manpower;
ü Site
engineer and project engineer
ü Fore
men
ü Unskilled
labours
ü Trainees
(PT students)
2.8.3 Time required
The work was required to be completed in a duration
of two (2) days.
2.8.4 Materials used, their sources and origin
ü High
tensile steel some of which were imported
ü Binding
wire
ü Stirrups
ü Spacer
blocks which were made in site.
2.8.5 Tools and machinery
The tools and machineries used were;
ü Pincer
ü Bar
bender
ü Tape
measure
ü Crane
for the high tensile steels to the second floor
2.8.6 Procedures
ü The
surveyor puts the marks of the shape of the column
ü The
required steels for a particular column are gathered and they are prepared
according to the bar schedule.
ü Then
the bars are tied to the starters by the binding wires
ü Afterwards,
the stirrups are inserted to the column reinforcements at the spacing of 200mm
from each other.
ü When
the work is completed the consultant asses the work for corrections and
approval
Note: the overlapping of reinforcement is determined
by a formula 50D where D is the diameter of the reinforcements (if they are equal
in size) and the diameter of the largest rebar (if they differ in diameter)
2.8.7 Influence of the environmental conditions
The environmental conditions were conducive hence
the work proceeded as planned.
2.8.8 Safety precautions
To ensure safety of the workers, they wore;
ü Helmet
ü Boots
ü Reflector
ü Gloves
2.8.9
Conclusion
0 Comments