SAMPLE INDUSTRIAL TRAINING REPORT



Projects are those works that was assigned to a certain company for the actual implementation at a given area. The company, as a consultancy services 
in Quantity Surveying and project management locally and globally, had several projects located at different places in Tanzania., Where one of the projects in which it was a consultancy services was a Renovation of Sisal building at UDSM main campus, Extension of JCC in UDMS main campus.
In this project, all practical training students were taken to the project to learn for some days. But also among of the project that I worked during PT 03 at AQE Associated Ltd office as follows-;
ü  Serengeti Media centre at Serengeti nation park
ü  Extension of JCC in UDSM main campus
ü  Njombe regional office block construction.
ü  BoT at Msese project
ü  Renovation of Sisal building at UDSM main campus  

WORKS PERFORMED IN THE PRACTICAL TRAINING PERIOD.
The works performed during the practical training;
ü  Preparation of Bidding Document
*      Measurement and preparation o Bill of Quantities
*      Preparation of consultancy estimate (pricing of bills)
*      Preparation of full of bidding document
*      Preparation of preliminary estimate (For another project)
ü  Preparation of payment valuation
ü  Preparation of financial appraisals
ü  Preparation final account
ü  Preparation of financial proposals
ü  Sorting out of contractual claims
ü  Site inspection and re-measurement and renovation
METHODOLOGIES
Methodologies used while learning was through-:
ü  Practicing.
ü  Literature view.
ü  Visualization and observation.
ü  Thoroughly consultation with other professional team and cooperation from my fellow students.
      CHALLENGES
ü  Modification of the building design which sometimes confuses during setting out and it affects the targeted time to accomplish the project
RECOMMENDATIONS
ü  The department in charge of the practical training should continue to assist students to obtain nice places where should be able to gain a lot of knowledge.
MAIN JOB; TAKING-OFF
1. INTRODUCTION
Taking-off are a detailed measurement of materials and labour needed to complete a construction project. They are developed by an estimator during the preconstruction phase. These measurements are used to format a bid on the scope of construction.   
The quantity “takeoff” is an important part of the cost estimate. It must be as accurate as
possible and should be based on all available engineering and design data.
We taking off quantities in accordance with Standard Method of Measurement of East Africa where by the units of measurement are: cubic metres, square metres, linear metres and numbered items. In addition, there are some items that are required to be recorded as items, which are descriptions without a quantity, for example plunking and strutting and dewatering.
The taking off sheet consists of four columns which are times, dimensions, squaring and description as explained below.
ü  The timesing column, which gives the factor of multiplication for the measurements in the dimension column.
ü  The dimension column, where the measurements are set down as taken from the drawings by starting with length(L) width(W) depth(D) accordingly.
ü  The squaring column, where the calculated total dimension after multiplication is written.
ü  The description column, where the description of the work or item in relation to the measurements is written as per SMM.
In our office of AQS Associates Ltd we performed taking off of different buildings of different categories such as single story for affordable semidetached houses and multi storey buildings. It involved substructure, walling, roofing, finishes, frame, door and windows, painting and decoration, external work (including pavement, soak away pits, septic tanks and fencing)
We performed this task using two methods which were:
ü  By using prepared taking off sheets (Manual)
ü  By using Microsoft Excel
The taking off by using Microsoft excel is an improved method where by special templates are prepared and make quick calculation such as addition, timesing, multiplication, division and squaring compared to manual method.
Consider example of Microsoft Excel taking off sheet in APPENDIX A1
1.      OBJECTIVE
The quantity “takeoff” is an important part of the cost estimate. It must be as accurate as
possible and should be based on all available engineering and design data.
2.      TIME REQUIRED
The time required was eighty hours per day.
3.      SKILLS AND MAN POWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
4.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of taking-off sheets by using Microsoft excel
ü  Note book-for taking note
ü  Architectural and structural drawings-where dimensions are taken from. 
5.      PROCEDURES
ü  Crosscheck the architectural and structural drawings in order to be familiar with the design,
ü  Writing taking off list,
ü  Taking-off quantities,
ü  Writing a queries list discovered during taking off some quantities,
ü  Report queries
6.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
7.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and its software
8.      CONCLUSION AND RECOMMENDATION
We acquired to get more improvement on using different techniques that lead to attain the required products.

MAIN JOB: PREPARATION OF BOQ
1.      INTRODUCTION
A BOQ’s is a document that lists and itemizes an estimate of how much material is needed, as well as manpower, equipment, profit needed to complete a construction project. Bill of quantities is prepared after taking-off well detailed drawing with its specification as per SMM and BOQ its used as a checklist for material, equipment, items and labour to be used during and after construction project processes.
There are different types of BOQ such as elemental, operational, annotated and trade/traditional bill of quantity.
In our office we prepared elemental BOQ. That bill consists of different parts such as preliminaries, measured work, day work, Prime cost and Provisional Sum and basic price list. 
During our preparation of BOQ, we build up the rate of the different items that involved the consideration of the material cost, labour cost, transportation cost, wastage and profit and overhead. Consider example in APPENDIX A2
This practical training led us to gain quick preparation of BOQ compared to before and we became more familiar with Microsoft Excel.
2.      OBJECTIVE
ü  The prime purpose of BOQ is to enable all contractors tendering for a contract to price on exactly the same information. Subsequent to this, it is widely used for post-tender work such as: material scheduling; and cost planning.
ü  Also due to the re-work involved in post-tender use of the BoQ `the extent of use` of the BOQ is important.
ü  Assist with the agreement of the contract sum with the successful tender.
ü  Provide a schedule of rate assisting with the valuation of variations.
ü  Provide a basis for the valuation of interim payments.
ü   Provide a basis for the preparation of the final account.

3.      TIME REQUIRED
Time required was eighty hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of BOQ by using Microsoft excel
ü  Note book-for taking note
ü  Taking-off quantities sheets
ü  Abstract sheets
6.      PROCEDURES
ü  Preparing taking-off quantities sheets
ü  Preparing abstract sheets by using taking-off quantities
ü  Preparing BOQ by using Microsoft excel and fill the quantities from the abstract sheet with respect.
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and its software
9.      CONCLUSION AND RECOMMENDATION
In order to help for avoids any ambiguities or misunderstanding and so help to avoid disputes arising through different interpretations of what has been priced.
It is very important that Bills of Quantity are should prepared according to a standard, widely recognized methodology.
The BoQ should identify the different kinds of work required, but should not specify them as this can lead to confusion between information in the BoQ and information in the specification itself.


1.      INTRODUCTION
  This is the work done by the consultant so as to value the work that is claimed by the contractor to be paid. Sometimes some of the consultant may complete the particular element and claim the amount that is greater than work done or he may claim the payment for the work that not yet performed (but this depend on the contract because some contract allows the claim for the anticipated work to be done)
The quantity surveyor from consultant’s side have to satisfy himself as do these respective percentages of work done are as performed. He may change percentage accordingly. It is not must that the amount claimed has to be paid as it is but depend on the final amount obtained by the consultant’s quantity surveyor.
There is different format that are used in performing valuation depend on the companies’ choice. Some of them include item, description, contract quantity, unit, previous quantity, current quantity, total quantity done, remaining quantity, percentage done, rate and amount.
Consider example in APPENDIX A3
We performed as work for the project of affordable houses for different units and different locations.
So the increment or omission of each item indicated with their respective amount.
2.      OBJECTIVE
ü  To allows an interim payment or payment valuation to be made.
ü  It is a detailed breakdown.
ü  To make stage payments to contractor.
3.      TIME REQUIRED
The time required was eight hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
6.      . PROCEDURES
ü  Visiting the site
ü  Checking that the work has been carried out either by measurement or by visual inspection.
ü  Check work packages
ü  Check variation
ü  Check special payments for off-site goods and materials
ü  Check acceleration cost 
ü  Check specific adjustments for advanced payments, work not properly executed, fluctuation, retention and so on
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software

9.      CONCLUSION AND RECOMMENDATION
The valuation for interim certificates should be made as accurately as is reasonably possible, and the contractor is entitled under the terms of the contractor to the full value of work executed on site, less a specified retention sum.
Also quantity surveyor should ensure timely and full payment for work carried out on site



MAIN JOB: PAYMENT VALUATION or CERTIFICATES
PREPARATION OF PAYMENT VALUATION or CERTIFICATES
1.      INTRODUCTION
Once the valuation of the work is done and the required amount that have to be paid to the contractor is determined by the consultant’s quantity surveyor, the payment certificate is prepared, this certificate will consist of the following:
Name of contractor and consultant with their addresses, the contract sum, adjustment of retention and advance payment, gross valuation, previous paid amount and amount due for the payment to the contractor in number and words.
Consider example in APPENDIX A4
Also this certificate must be signed by the Architect. The copy of this certificate shall be submitted to employer, contractor, consultant’s project manager, architect, Qs and to the file.
2.      OBJECTIVE
ü  To ensure the contractor is paid for work done at regular intervals.
ü  To be used in the great majority of building contracts as the contractor should not have to finance complete works.
ü  To certify the quantity of work done to date, on which payment is made.    
3.      TIME REQUIRED
           The time required was eight hours per day
4.      SKILLS AND MANPOWER
           The activity involved the following 
ü   2 Quantity surveyor
ü   5 students

5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
ü  Interim valuation of the constructed work.
ü  BoQ
ü  Periodic payment

6.      PROCEDURES
ü  Timing of payment claim
ü  Amount of interim payment
ü  Check components of interim payment such as; Preliminaries, measured works, Value of variation, Value of day works, Value of unfixed materials, Value of contractual claim Labour and materials price fluctuation, Retention and Value Added Tax
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software
9.      CONCLUSION AND RECOMMENDATION
The valuation for payment certificates should be made as accurately as is reasonably possible, and the contractor is entitled under the terms of the contractor to the full value of work executed on site, less a specified retention sum.
Also quantity surveyor should ensure timely and full payment for work carried out on site.
MAIN JOB: FINANCIAL APPRAISALS
PREPARATION OF FINANCIAL APPRAISALS
1.      INTRODUCTION
General Financial Appraisal is a method used to evaluate the viability of a project by assessing the value of net cash flows that result from its implementation.
Financial Appraisals is the document that is prepared by the consultant’s QS so as to determine the actual financial position at the existing time. It is used to indicate if the project is below or above the budget at that time. How much extra money is needed to be added by the client so as to finish the project. if this document indicates that project is above the budget, the consultant’s QS has to find different alternatives so as to end up the project within the budget.
This document is prepared after every three months or four months, etc depending on the contract agreement.
Consider example in APPENDIX A5

2.      OBJECTIVES.
ü  It alerts the client on the financial position.
ü  It alerts quantity surveyor so as to come with alternatives for the remaining work so as to avoid the project to run over the anticipated budget.
3.      TIME REQUIRED
The time required was eight hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
ü  Stage payments against calendar dates
ü  Measurement against
ü  Activity schedules
ü   BoQ

6.      PROCEDURES
Identify the time horizon
Identify the incremental cash inflows and outflows for
each steps
Quantify the costs
Identify the partner and discount the cash flow
Sensitivity analysis
Reporting 
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software
9.      CONCLUSION AND RECOMMENDATION
If this document indicates that project is above the budget, the consultant’s QS has to find different alternatives so as to end up the project within the budget.
This document is prepared after every three months or four months, etc depending on the contract agreement.

MAIN JOB: SCHEDULE OF MATERIAL
1.      INTODUCTION
Schedule of material is the schedule that shows the quantities of materials that needed to be used in the particular projects. Some of schedule of materials involve price of each item.
In our office, we prepared schedule of materials of different items in such a way that we quantify the amount of each component and item involved. Example for the concrete, we quantify the amount for the sand, aggregates and cement. For the block wall, amount for the blocks, sand and cement.
Finally, we put their respective rate and amount for each item and component involved in a particular work. Consider example in APPENDIX 6
2.      OBJECTIVE
ü  To identify the materials needed in order to accomplish the construction project
ü  Also in preparation of the quantity, we provide allowances of wastage in percentage depending on the nature of material.
3.      TIME REQUIRED
The time required was eight hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
6.      PROCEDURES
ü  Preparing taking-off quantities sheets and Preparing BOQ
ü  Identify quantity of material required from BOQ
ü  From the total quantities of materials find number of trip or piece by consider waste of the such kind of material
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software
9.      CONCLUSION AND RECOMMENDATION
It should have prepared from the quantities present in the BoQ

MAIN JOB: FINAL ACCOUNT
1.      INTRODUCTION
PREPARATION FINAL ACCOUNT
Final account is the document that is prepared by the consultant’s quantity surveyor that states the actual amount used for the particular project. This is done at the end of the project i.e. after defect liability period. This amount may differ from the anticipated lump sum that indicated during the signing of the contract.
This document comprises of different items including the total amount of omission and addition for different elements involved such as preliminaries, measured work, contingency, PC and provisional sum.  Also it includes the name and addresses of the consultant and contractor, original anticipated contract sum, etc.  It can be presented using different format
 This document states the actual amount that used for the particular project, hence the client is ought to pay that amount. This amount may be more or less than anticipated value but it is the responsibility of the quantity surveyor to ensure that the anticipated contract sum is not exceeded.
Consider example in APPENDIX A7.
2.      OBJECTIVE
ü  To state the actual amount that used for the particular project
3.      TIME REQUIRED
The time required was eight hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
ü  Payment valuation

6.      PROCEDURES
Check total amount of omission and addition for
different elements involved such:
ü  preliminaries
ü  measured work
ü  contingency
ü  PC
ü  provisional sum
Adjustments for element mentioned above
Less VAT from contract BOQ
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software
9.      CONCLUSION AND RECOMMENDATION
We prepared this document just theoretically as there was no any project that was at the finishing stage

MAIN JOB: CASH FLOW PROJECTION FINAL ACCOUNT
1.      INTRODUCTION
Cash flow projection is the anticipation of the flow of the money for the entire time of the project, it estimates how much shall be requiring to be used in each month after adjustment of the retention and advance payment (if was taken by the contractor)
This prepared by the consultant’s quantity surveyor just before starting of the project. This cash flow shall be updated accordingly.
Consider example in APPENDIX A8
2.      OBJECTIVE
ü  This is used to alert the client on the anticipated flow of the money for his/her project
3.      TIME REQUIRED
The time required was eight hours per day
4.      SKILLS AND MANPOWER
The activity involved the following 
ü   2 Quantity surveyor
ü   5 students
5.      MATERIALS, TOOLS AND EQUIPMENT USED
ü  Calculator –for calculation
ü  Pen and Pencil-for writing
ü  Computer system-for preparation of sheets for quantities by using Microsoft excel
ü  Note book-for taking note
6.      PROCEDURES
ü  Preparing taking-off quantities sheets and Preparing BOQ
ü  Identify quantity of material required from BOQ
ü  From the total quantities of materials find number of trip or piece by consider waste of the such kind of material
7.      INFLUENCE OF ENVIRONMENT.
 The influence of the weather was positive to the progress of the work, no any condition which could compromise the work. 
8.      SAFETY PRECAUTIONS.
During working on this activity several safety precautions were considered including,
ü  Protect laptop
ü  Protect computer system and it`s software

PREPARATION OF PAYMENT VALUATIONS.
Preparing Interim Payment Valuation for Construction Works.
An interim (stage) payment is a payment on account of the compensation due to any party to a construction contract that has a duration accordingly the contract, interim payments ease the contractor`s cash flow, on the premise that project finance is cheaper for the client than it is for individual contractors and the basis of the contractor`s interim valuation (application for payment) will vary depending on the type of contract being used.
Payment certificate in construction is a document verified by an Architect, Engineer or owner of a construction project that the noted work has been completed and is approved for payment by the general contractor. 
The effective administration of the payment clause of a building contract is one of the most important tasks that the contract administrator and consultant quantity surveyor perform during the contract period. The importance of cash flow within the construction supply chain is key to the smooth running of a contract. The Act’s primary purpose is to ensure that contractors, and more particularly subcontractors, are paid promptly, and in full, for work that they have carried out. The Act requires construction contracts to provide an ‘adequate mechanism’ for calculating both the timing of payments, and the amounts to be paid. If such a mechanism is not included in the agreement; the procedures set out in the ‘Schedule’ to the Act are deemed to apply. The default arrangements in the Schedule require contractors to be paid within 30 calendar days of submitting a payment claim. The default provisions in the Schedule apply to all subcontract payment agreements, unless more favourable terms than those set out in the Schedule can be secured. The Act also outlaws previous widespread payment practices such as pay-when-paid conditions. The primary impact of the Act, therefore, may be viewed as enshrining interim payments as the standard means of paying for construction work in order to generate the vital cash flow required by the supply chain.
There is no specific of an ‘adequate mechanism’ for payment but it is supposed that a number of common approaches would satisfy the requirements such as:
Ø  regular predetermined set periodic payments;
Ø  Stage payments, which are predetermined payments made following the completion of specific sections of the work;
Ø  detailed interim valuations of the construction work in progress.

Stage payments
This approach pays agreed amounts of money when certain stages of the work are finished. For example, on completion of the substructure or when the building is weather-tight. This approach is also simple to operate and does not overvalue the works. However, it does not include for further work in progress and materials on site. Non-completion of minor items of work within a stage could also hold up the payment for the entire stage. (Hackett et al. 2007)
Timing of Payment Claims
The Contractor initiates the payment process by submitting a detailed progress statement to the Architect, valuing the work, including sub-contract work, completed at the payment claim date. On most projects the task of checking the valuation will be carried out by the Employer’s consultant quantity surveyor. This task must be attended to promptly, as the Contract requires the Architect to issue a Certificate within the timescale set out in the APPENDIX to the Contract. This default period for ‘turning around’ valuations is five working days.
Amounts of Interim Payments.
The Contract Clause sets out the procedures for valuing the content of interim certificates; in brief this covers the value of the work ‘duly’ (properly) executed and the materials delivered since the previous valuation. Duly executed work includes elements such as preliminaries, provisional work, prime cost work, works covered by architect’s instructions, material and labour price fluctuation claims, and loss and expense claims.
The payment comprises ‘the Contract value of the Works properly executed’, plus an evaluation of unfixed materials, and ‘Compensations Events’.
Commentary The consultant quantity surveyor’s role is to check the contractor’s valuation and issue a certificate recommendation to the contract administrator in accordance with the terms of the particular contract. The quantity surveyor must make a fair valuation of the work. While interim valuations are not conclusive, they must be a fair and reasonable assessment of the value of work done. Care must be taken not to over-value or under-value the work. Under-valuation reduces vital cash-flow to which the Contractor is entitled. Over-valuation on the other hand risks the Employer’s position in the event that the Contractor defaults and fails to complete the Works. In this event the Employer may have to pay a completion contractor for work and materials, for which the original contractor has already been paid.
The QS must visit site to verify that the work claimed for has actually been carried out, and that the contractor’s application for payment is arithmetically correct. A general appraisal should also be made as to the overall level of the valuation - bearing in mind progress on site and the projected cash flow. The certificate recommendation must also separately identify payments for nominated / specialist sub-contractors.
It is common for the QS to disagree with the Contractor’s valuation and adjust it, and in these instances, the Architect must explain the differences specifying the reason or reasons for the difference and the basis on which the amount certified for payment is calculated. It should be noted that the Act`s requires the Employer to submit a written response to a payment claim notice (a withholding notice or pay-less notice) in order to contest a contractor’s payment claim.


Periods for Honouring Certificates.
The Employer’s primary contractual duty is to pay the Contractor.
Under the Act`s Contract, as soon as the Architect’s interim certificate is presented to the Employer, the Employer must pay the Contractor within mentioned working days (unless another period is stipulated in the APPENDIX). Failure by the Employer to pay on time entitles the Contractor after mentioned working days to claim
Failure by the Employer to pay on a certificate is a ground for the Contractor to threaten to suspend work, and subsequently determine its employment under the building contract (subject to notice). The Employer does not have the right to obstruct or interfere with the issue of any Architect’s or Employer’s Representative’s certificates. The Architect / Employer’s Representative should advise employers as to their responsibility regarding honouring certificates before commencing construction. Where the project is funded in whole or in part by grant aid, e.g. school contracts, the Architect should advise the Employer as to the obligations to honour certificates whether grants have been paid or not.
Retention
The Act`s Contract clauses set out various procedures for dealing with retention money which is set aside in order to rectify defective work. Retention is normally held as a percentage of the value of the executed work and materials. The amount of the retention held may be capped if a particular limit is stated in the APPENDIX. The insertion in the APPENDIX states that the retained percentage is ‘not to exceed 10%’
The most common option for dealing with retention is set out in clause This sub clause provides that retention is held on ‘the value of the work and materials’ by the Employer during the construction phase of the project. The retention is held on trust for the Contractor by the Employer who is not obliged to invest this money. One moiety (half) of the retention is released on Practical Completion of the Work. The other half of the retention is released on foot of the Final Certificate.
.
In addition, sub-clause sets out a further mechanism for dealing with the remaining retention held after the issue of the Certificate of Practical Completion. Under this arrangement the Contractor provides an approved retention bond which triggers the full release of the remaining retention.
It should be noted that a number of components of a valuation are not subject to retention. These include: reimbursement of fluctuation claims, reimbursement of contractor’s loss and expense claims, and payment for remedial work in connection with damage covered by the Contractor’s all risks insurance Fees or charges legally demandable by local and other authorities and similarly performance bonds where separately identified would not be subject to retention.
3.3 Components of Interim Payments
The Quantity Surveyor should always visit and walk around the site, accompanied by the Contractor’s Surveyor whenever possible. He/she should also talk to the Clerk of Works (if one has been appointed) or other design team members on site before starting the valuation.
It is common for the Contractor’s Quantity Surveyor and the Client’s Quantity Surveyor to discuss and agree these interim valuations before they are forwarded to the Architect (Project manager) for certification. The QS must separately identify the amounts included for named specialists or nominated subcontractors work included within the interim certificate recommendations.
Preliminaries
Preliminaries refers to the contractor’s costs in running the building site. The ‘prelims’ refer to costs which are necessary but do not form part of the completed building. These represent the contractor’s site overheads and temporary costs and include matters such as: site staff, security, hoarding, temporary roads, site accommodation, insurance, plant, site cleaning and so on.
Items included in the preliminaries may be fixed costs or time related costs and several items contain both fixed price and time related cost components. Some preliminaries items such as the provision of a bond, drying out the work, cleaning site on completion for example, are fixed costs. Other items, such as the cost of site staff are largely time-related and depend on the estimated length of time the staff will spend on site. Other items, again, incur both fixed costs and time related costs, for example scaffolding incurs erection costs (fixed cost), maintenance (rental / time dependent costs) and final removal / striking costs.
In practice the preliminaries are often valued pro-rata to the percentage of the building work which has been carried out. This approach may, however, be unsatisfactory for contractors, particularly on contracts with substantial start-up costs. Ideally an itemized break-down of the prelims can be agreed prior to the start of the works. This breakdown will ensure a greater degree of accuracy in the valuation of the preliminaries and enable the contractor to promptly pay for ‘point’ costs as they occur.
Measured work
This component involves valuing the completed works on site. The simplest method is to visually assess the estimated percentage of the work completed within each element of the pricing document. For example, 50% of substructure and 30% of external walls and so on. Although this produces a crude valuation it is a widely used technique. Where greater accuracy is required the progress of the individual work items can be measured on site. On Act`s contracts, provisionally measured work and the expenditure of provisional sums must also be promptly re-measured, valued and kept fully up to date as part of the measured works category.
Ashworth, Hogg and Higgs (2013) comment regarding the need for accuracy, advising that ‘the surveyor should appreciate that an interim valuation is merely a snapshot of the progress of the works, which … change significantly within 24 hours of the assessment’. They add that ‘It should be remembered that detailed measurement for valuation purposes will likely have no further bearing beyond the interim payment in hand and is therefore of passing value only.’
Nominated subcontractors and suppliers work
On Act`s contracts nominated subcontractors and suppliers are paid by the main contractor. The valuation of each nominated subcontractor’s work is identified separately on both the quantity surveyor’s recommendation and the architect’s certificate. The main contractor is entitled to a pro rata proportion of the profit and special attendance on the nominated account where these are priced in the tender. 
On public works contracts, although named specialists are considered to be ‘domestic subcontractors’ the value of their work must be separately identified in the Employer’s Representative’s certificate.
Value of variations / change orders
It is almost inevitable that there will be design modifications and changes as the works progress. Variations arise where the contract administrator issues a written instruction directing the contractor to carry out additional or substituted work, or to omit work. Verbal instructions should be confirmed promptly in order to authorise payment. Variations should be measured and valued as soon as possible and should be routinely agreed and signed off by the parties to the contract. It is common, however for valuations to include on-account payments for some variations until they are properly valued at a later stage.
Value of dayworks
Occasionally, it may not be appropriate to use or adjust contract rates to value particular works and it may be necessary to value these on a time and material basis. This approach is referred to as dayworks. Dayworks involves the contractor recording the resources used to perform the particular task; i.e. the hours worked by the various operatives, craftsmen, labourers etc. and the plant and materials used. All daywork sheets, should be properly priced in accordance with the contract provisions, and approved by the contract administrator before they are paid.

Value of unfixed materials
As noted above, the Act`s contract, generally entitles the Contractor to be paid for unfixed work materials delivered to the site. Payment for materials stored off site, however, is at the architect’s discretion and may be included in the valuation provided the required safeguards have been fully satisfied.


Value of contractual claims.
The main contractor may be entitled to additional payment for loss and or expense suffered as a direct result of any delay or disruption to the works caused by the employer or the design consultants. It is up to the contractor to prove the loss and expense to the contract administrator’s satisfaction. Loss and expense claims are often contentious and may take considerable time to resolve. Nevertheless, the contract administrator must include a fair and reasonable valuation of the contractor’s reimbursement claim in interim certificates pending final agreement of the claim.
Loss and expense claims are not subject to retention on Act`s contracts.
Labour and material price fluctuations.
Claims for fluctuations in the price of labour and materials are rare in practice, as this risk is typically transferred to the contractor on private sector projects when finalising the contract negotiations. The arrangement is achieved by striking out Clause of the Act`s contract conditions. Where fluctuation claims are admissible under the Act`s Form, the Contractor can apply for payment of increases in the interim progress applications. The contract rates are deemed to be set at the ‘designated date’ set out in the APPENDIX. If wages, or the rates of ‘other emoluments’ rise, the extra costs can be recovered. The prices of materials at the time of the tender are deemed to be market prices and a list of such basic prices may be required. If prices increase during the course of the contract the increases are recoverable. If there is a substantial increase in the price of any goods, the Contractor shall give notice in writing to the Architect within a reasonable time of becoming aware of the of an increase. A percentage addition of 7.5% is applied to labour accounts and 12.5% is applied to material increases to cover the associated irrecoverable items and the cost of preparing the account.
Fluctuation claims are not subject to retention under the Act`s contract.
Retention
The client normally retains a percentage of the gross valuation of the works, to cover the rectification of defective work and ‘snags’. 

Value added Tax
General construction work is subject to VAT, which is currently 18%age
Previous payments to contractor
The sum due to the main contractor is the gross valuation adjusted for retention (If it`s applicable) and VAT (If it`s applicable) less amount previously paid.
ü  Modification of the building design which sometimes confuses during setting out and it affects the targeted time to accomplish the project.
ü  Some activities that we did were not at current stage, just we did by theoretical means such as:
                                       Preparation of cash flow projection documents
                                       Preparation of final account
                 4.2 RECOMMENDATIONS
ü  The department in charge of the practical training should continue to assist students to obtain nice places where should be able to gain a lot of knowledge.
ü  The IT coordinators should find effective offices that have the active project during the field period. This doesn’t mean that we did not have works to do. We did a lot but some of our friends who did in some offices, they did only few parts concerning with the office work.
ü  The programme of work (Microsoft project) should be taught practically to QS students with associated assignments because sometimes contractor’s QS may be ought to prepare and update the programme of work.
               4.3 CONCLUSION
This Industrial Training for the office work is very important as it makes the student to be knowledgeable and competent for the actual practice done in construction. This helps us to know in deep how the construction offices work.


Post a Comment

0 Comments